San Francisco Chronicle

Litany of errors at Oroville Dam

Decades of complacenc­y, inadequate repairs caused near-disaster, report finds

- By Kurtis Alexander

The spillway failures at Oroville Dam that prompted tens of thousands to flee for their lives last winter were the result of years of mistakes, lax inspection­s and lazy repairs by the state’s water agency, a team of independen­t dam experts reported Friday.

Their conclusion­s: State water managers should not have built the dam’s primary spillway on faulty bedrock. They should have done more when the spillway’s concrete began to crack and water seeped through. And they should have been on high alert when the ground below began to give way.

Instead, during nearly 50 years of preventabl­e decay, the California Department of Water Resources did only a few patch jobs on the half-milelong water chute, leading up to its disintegra­tion in February and prompting wider concern about how the state maintains its other nearly three dozen water storage sites.

The six-person team charged by federal regulators with investigat­ing the nation’s tallest dam has pointed out several of the structural deficienci­es in previous reports, but its latest and final assessment links them to a steady run of human missteps.

The 584-page document describes a culture of complacenc­y, overconfid­ence and insularity at the Department of Water Resources that allowed errors to compound earlier errors, dating back all the way

to the dam’s constructi­on in the 1960s.

Although the authors say state managers had numerous opportunit­ies to prevent spillway problems, they don’t blame any individual. Nor do they identify a single root cause behind the dam’s flaws.

“Although we’re recommendi­ng that DWR look at its organizati­on and improve, many of the lessons apply to other dam owners as well,” said John France, a geotechnic­al engineer and head of the review team. “As a group, our industry needs to improve what we’re doing.”

State water officials said Friday they are still reading the report but that they take the findings seriously.

“As we have done in the past, we will carefully assess this report, share it with the entire dam safety community and incorporat­e the lessons learned going forward to ensure California continues to lead the nation on dam safety,” said Grant Davis, director of the Department of Water Resources.

The report notes that the Federal Energy Regulatory Commission, the agency tasked with inspecting all dams that generate electricit­y, also failed to spot long-standing issues at Oroville Dam, as did several consultant­s who worked with the state.

The report calls the repeated oversights a “wake-up call” for everyone responsibl­e for dam safety.

“People should not lose sleep over this, but they should be concerned,” France said.

The problems at 770-foottall Oroville Dam, located about 75 miles north of Sacramento, became obvious to everyone on Feb. 7. A section of the giant spillway fractured as large volumes of water poured out of the reservoir, prompting dam operators to turn to an emergency spillway, essentiall­y a barren hillside, to make releases. The backup chute, however, also began to fall apart.

Fears that water would pour uncontroll­ably out of the lake prompted officials to order evacuation­s for 180,000 people living downstream.

The new report takes issue with how state water officials handled the crisis as well. The slopes of the emergency spillway were geological­ly unsound and not tested, according to the document, and dam operators should not have allowed water releases there.

As it turns out, dam operators were able to use the broken main spillway to make safe releases and prevent the reservoir from overflowin­g. The report’s authors say the primary chute should never have been taken out of service.

“The decisions were made with the best of intentions,” the report said, “but against the advice of civil engineerin­g and geological personnel.”

The panel’s assessment dates the issues at the dam to even before the first concrete was poured. The ground beneath both the primary and backup spillways was not as strong as it should have been, the authors say, and few at the Department of Water Resources took note initially or in the ensuing years.

“Although the poor foundation conditions at both spillways were well documented in geology reports, these conditions were not properly addressed in the original design and constructi­on, and all subsequent reviews mischaract­erized the foundation as good quality rock,” the report said.

The person who designed the spillway, the report said, had only “limited experience” with such work.

Shortly after the dam was built, cracks emerged on the main spillway, according to the assessment. Rather than recognize a problem, dam managers assumed the fractures were normal.

The report identifies five fixes that were done on the main chute as the cracks widened, one as late as 2013. But none got to the heart of the problem. According to the panel, water seeped into the ground and slowly ate away at the soil and the spillway’s anchors. In addition, the drains proved insufficie­nt.

The dam’s damaged spillways have since been mostly rebuilt in what amounted to one of the fastest constructi­on projects in modern state history. The costs so far have totaled $500 million.

In the wake of February’s scare, state water officials have begun a review of Oroville Dam as well as evaluation­s of spillways at other reservoirs.

 ?? Rich Pedroncell­i / Associated Press 2017 ?? Oroville Dam’s spillway failures resulted from neglect at the Department of Water Resources, a report says.
Rich Pedroncell­i / Associated Press 2017 Oroville Dam’s spillway failures resulted from neglect at the Department of Water Resources, a report says.
 ?? Scott Strazzante / The Chronicle 2017 ?? Water flows out of Oroville Dam’s damaged spillway in February. A team of experts cited almost 50 years of preventabl­e decay.
Scott Strazzante / The Chronicle 2017 Water flows out of Oroville Dam’s damaged spillway in February. A team of experts cited almost 50 years of preventabl­e decay.
 ?? Carlos Avila Gonzalez / The Chronicle 2017 ?? Thousands of gallons of water rush over the main and auxiliary spillways at Oroville Dam in February. Thousands of people were forced to flee for their lives when the spillways fractured.
Carlos Avila Gonzalez / The Chronicle 2017 Thousands of gallons of water rush over the main and auxiliary spillways at Oroville Dam in February. Thousands of people were forced to flee for their lives when the spillways fractured.

Newspapers in English

Newspapers from United States