San Francisco Chronicle

No completion date yet for S.F. subway

- By Gwendolyn Wu

Muni’s longawaite­d $1.6 billion Central Subway project has a new manager just six months before the oftdelayed project is scheduled to be completed — and there’s a chance the grand opening could get pushed back again.

Nadeem Tahir took over as project manager last week after previous stints with the D.C. Metro subway, Honolulu Rail Transit and the Federal Transit Administra­tion. On a media tour Thursday, while more than 100 workers were laying down sections of track and building elevators, San Francisco Municipal Transit Agency officials introduced Tahir and showed off the stillunder­constructi­on Union Square Station, an echoing concrete concourse filled with halffinish­ed elevators and escalators.

The completion of the Central Subway, which broke ground in 2010 and will reroute Muni’s TThird light rail line from the Bayview up to Chinatown, has been plagued with delays due to problems with general contractor Tutor Perini and existing infrastruc­ture issues.

Officials stopped short of saying the transporta­tion project is behind schedule, but Tahir and acting Muni director Tom Maguire said it would take another six weeks to pinpoint the subway’s completion date.

“Any date that I throw out I don’t think we’ll have thoroughly researched,” Maguire said Thursday

When the project began, Muni officials said passengers would be able to board the trains by the end of 2018. The current projection for opening the Central Subway is January 2020. Transit officials will then have to evaluate the safety of the structures, trackway and rail systems.

Maguire said merchants who long have complained about the burden of constructi­on on busi

nesses along the Stockton Street corridor will appreciate the completion of work in the fall.

“They’re going to have a street that’s clean and free of constructi­on,” he said.

Abovegroun­d constructi­on has snarled traffic on Stockton Street between Geary and Ellis for years, with that section of Stockton Street only recently reopening to buses and cars.

It’s unclear whether the Central Subway will stay within its $1.6 billion budget. An independen­t federal monitor report analyzing the project said officials had spent nearly all of the federal grant money as of the spring.

“Additional contingenc­y will probably need to be allocated to this contract prior to completion,” the report said.

Officials said they took the findings seriously but noted the report is “not the complete picture.” An updated projection on costs and completion date is expected within the next six weeks.

“There are a lot of interconne­ctions between the work that we have to do for operations and as far as the physical constructi­on,” Tahir said.

Thursday’s tour suggested plenty of work remains to be done on the 900footlon­g station, which was still dark and dusty, with plywood boards on the concrete slab floor and exposed walls lining the tunnel.

The escalators and elevators that will ferry passengers from the surface and concourse levels are still being built, and workers could be seen laying down the track, which will extend the existing train line 1.7 miles. Union Square Station is expected to connect to Powell Street Station via an undergroun­d pedestrian walkway.

Former project manager

“Any date that I throw out I don’t think we’ll have thoroughly researched.” Tom Maguire, acting Muni director, on when the subway might open Gwendolyn Wu is a San Francisco Chronicle staff writer. Email: gwendolyn.wu@ sfchronicl­e.com Twitter: @gwendolyna­wu

Albert Hoe estimated the station’s tracks, electrical and mechanical systems would be finished by the middle of 2019.

Transit officials said they are resolving complaints from contractor Tutor Perini, which told San Francisco supervisor­s in 2017 that the project was running over budget and falling even further behind schedule.

Tutor Perini officials requested $112 million in change orders, exceeding the $79 million budget Muni allotted.

“No project gets done without a certain amount of conflict,” Maguire said.

Tahir is the third manager of the project following Hoe, who took over as the Central Subway’s acting project manager after John Funghi left in 2017 to oversee the electrific­ation of Caltrain.

 ?? Photos by Jana Asenbrenne­rova / Special to The Chronicle ?? The Union Square/Market Street Central Subway Station is still months away from opening, officials said.
Photos by Jana Asenbrenne­rova / Special to The Chronicle The Union Square/Market Street Central Subway Station is still months away from opening, officials said.
 ??  ?? The escalators and elevators from the surface to concourse level at the station are among the projects still in progress.
The escalators and elevators from the surface to concourse level at the station are among the projects still in progress.
 ?? Photos by Jana Asenbrenne­rova / Special to The Chronicle ?? Ground was broken on the Central Subway in 2010, but it remains months away from being ready for its grand opening.
Photos by Jana Asenbrenne­rova / Special to The Chronicle Ground was broken on the Central Subway in 2010, but it remains months away from being ready for its grand opening.
 ??  ?? Workers at the Union Square/Market Street Central Subway Station plan their next actions Thursday.
Workers at the Union Square/Market Street Central Subway Station plan their next actions Thursday.

Newspapers in English

Newspapers from United States