San Francisco Chronicle

S. F. Muni tunnel fix needs costly redo

- By Mallory Moench

The San Francisco Municipal Transporta­tion Agency has long struggled to complete vital constructi­on projects and fix equipment failures, but the problems are worse this year amid a pandemic and fiscal crisis, contractor stumbles and past decisions creating present headaches, city leaders and advocates say.

This week, the agency revealed to city supervisor­s that part of Twin Peaks Tunnel will need to be replaced — just two years after a major $ 50 millionplu­s renovation of the tunnel was completed.

The backtrack will cost tens of millions of dollars, take three months and slow the restart of the light rail system, which abruptly shut down in August due to equipment failures. The shutdown came two days after the light rail was reopened, but the need to replace broken splices, which connect

overhead wires, will keep it closed into next year. The SFMTA will not bring back subway service before the Twin Peaks Tunnel is completed in February and will phase in abovegroun­d light rail and bus service first, spokeswoma­n Kristen Holland said.

In addition to the tunnel and light rail fiascos, last week the agency pushed back the opening of the Central Subway project from next year to 2022 because of COVID19-related delays.

Exasperate­d city supervisor­s, who also serve as the San Francisco County Transporta­tion Authority board, demanded this week that the agency do better.

“It is just extraordin­ary that this amazing city seems unable to deliver a transporta­tionrelate­d capital project,” Supervisor Rafael Mandelman said during a meeting of the board on Tuesday. “We can’t continue like this.”

City leaders, SFMTA staff and transit advocates this week said problems include a policy of taking the lowest instead of the best contract bid, failure to manage contractor­s well, missing communicat­ion between engineerin­g and maintenanc­e department­s, weak oversight of the capital projects division and no clear chain of command on interagenc­y projects.

The agency’s director of transit, Julie Kirschbaum, presented a plan for longterm subway investment­s and improvemen­ts Tuesday and told the board the agency needs “significan­t improvemen­t in project delivery.”

“It’s an area we know we need to do better on,” she said. “We don’t have all the answers now.”

SFMTA Director of Transporta­tion Jeffrey Tumlin, who took over leadership last year, said he inherited some problems and is now responsibl­e for all of them, including what he called a “culture of fear.”

“This is something I’m working very hard to correct,” Tumlin said. “Employees are afraid to diagnose the problem and elevate it because that might make us look bad. Well, nothing makes us look worse than failing to deliver decent service or deliver a project on time.

“All of that must be resolved before we go to the voters and say trust us with more capital money,” he added.

Tensions were evident at Tuesday’s meeting after agency staff told the board that part of the Twin Peaks Tunnel upgrade needs a redo after the original project didn’t replace a part as planned.

The 2.2milelong Twin Peaks Tunnel is the conduit for four of the city’s most heavily used light rail lines, carrying more than 80,000 passengers per weekday before the pandemic. The tunnel, constructe­d in 1918, was upgraded in 2018 with seismic retrofitti­ng and structural replacemen­ts at the cost of around $ 50 million. The monthslong project resulted in service interrupti­ons and the death of a Muni constructi­on worker.

SFMTA officials said that during the project, contractor­s and staff chose to reuse the ballast, the rocky bed beneath the tracks that stabilizes the trackway and allows drainage to trickle through, instead of replacing it as intended. The decision, which was meant to save time and money, was not flagged for upper management, Kirschbaum said. If the ballast had been cleaned, it might have been costand time-effective, but it wasn’t, and now it’s more mud than rock, she said.

The work to replace the ballast will run from Nov. 30 through February 2021, with crews working six days a week.

Agency staff were slammed at the transporta­tion authority board meeting over the project that Supervisor Aaron Peskin and others called a “screwup.”

“You’re out of excuses,” Peskin said.

Cat Carter, spokeswoma­n for advocacy group SF Transit Riders, said delays to complete projects and fixes after they’re finished “seem chronic.” She blamed historic mismanagem­ent, lack of transparen­cy and underfundi­ng for public transporta­tion, only worsened by the pandemic that has left SFMTA with a $ 30.7 million budget deficit unless more federal relief comes in.

“Transit is going to be essential to recover the economy,” she said. “It’s facing a financial cliff without having to go back and fix ballasts.”

The SFMTA is already underfundi­ng maintenanc­e. Jerad Weiner, the agency’s asset management unit manager, told the transporta­tion authority board in September that eliminatin­g a $ 3.2 billion backlog in equipment replacemen­ts will take two decades. The agency would need to triple its annual investment to get it done, he said.

SFMTA leaders said they are trying to learn as much as they can from past delays and failures. Supervisor­s pushed the agency to find more solutions.

“I want the MTA to have a way of holding the MTA accountabl­e,” Mandelman said.

 ?? Paul Chinn / The Chronicle 2018 ?? Muni Metro light rail trains stop at the West Portal Station at one end of the Twin Peaks Tunnel, which needs more repairs.
Paul Chinn / The Chronicle 2018 Muni Metro light rail trains stop at the West Portal Station at one end of the Twin Peaks Tunnel, which needs more repairs.

Newspapers in English

Newspapers from United States