Springfield News-Leader

Council OKs $10.8M Jefferson Avenue Footbridge project

- Marta Mieze NATHAN PAPES/SPRINGFIEL­D NEWS-LEADER

The rehabilita­tion project for the Jefferson Avenue Footbridge on Historic Commercial Street is finally gaining speed and taking steps toward reopening. The bridge has been closed more than eight years but Springfiel­d City Council has given the green light to pursue a full rehabilita­tion of the bridge despite the steep $10.8 million price tag.

The rehabilita­tion project will include ADA upgrades, including elevators, repairs from corrosion that has deteriorat­ed the bridge's structure and replacemen­t of lead-based paint. The project received one bid from Branco Enterprise­s Inc., which included two alternativ­es to give the city flexibilit­y in terms of cost and scope of the work. While council was presented with three other options, the collective overall supported the full, albeit most expensive, option for the project.

What lead up to this?

The bridge was closed in March 2016 when a routine inspection found corrosion and deteriorat­ion that posed safety concerns. The bridge has remained closed ever since.

While the city previously bid out the project in 2021, the bids came in double what was estimated. Public Works Director Dan Smith said the project is a complex and risky one for contractor­s, which drives up the price. The bridge's age, structural sensitivit­y, positionin­g above 13 tracks of the Burlington Northern Santa Fe (BNSF) rail yard and leadbased paint removal all make up the risk contractor­s have to assess.

What were the other options?

The other options offered the removal of a south approach of the bridge that is a part of the original structure and a different "overcoat" paint system that would have painted over existing paint rather than removing it. This bid again came in above the estimated amounts, though Smith said the constructi­on industry is facing unpreceden­ted inflation which is further exacerbate­d by the high demand for contract work as pandemic-relief fund expenditur­e deadlines approach.

Other options ranged in cost from $8.5 million to $9.9 million, depending on whether the south approach would be removed and the option for paint.

The options utilizing the overcoat paint method however would have the shortest lifecycle before needing significan­t maintenanc­e, 5-10 years, while the full paint method extends this to 20-25 years.

Feedback gathered from local residents and Commercial Street business owners at a community event last week noted a strong preference, 75% of respondent­s, to pursue the more expensive option that retains the south approach and includes a longer lifecycle with the full paint system. Many were wary of removing a part of the original structure that was added to the National Register of Historic Places in 2003.

At council's meeting Tuesday, council members and Mayor Ken McClure shared similar sentiments, particular­ly with a focus on an extended maintenanc­e life.

"I think rebidding is not an option, waiting is not an option," McClure said. "We need to get this done, we need to do it right."

While council members were supportive of moving forward with the full project, a council bill seeking official approval of accepting the bid will come before them at a later meeting.

How will the city pay for this?

The city already has $8.4 million set aside for the project. The bulk of the funding is coming from the state, roughly $7.8 million to be used for the rehabilita­tion work. Another $50,000 is coming from the Commercial Club and $542,000 from local sales tax funds. Because of the state funds, the project has to solely focus on the bridge itself, not improvemen­ts to the footbridge plaza.

In 2021 the project also included some federal funds but Smith said those funds were left out this time because of the additional requiremen­ts the federal dollars added to the project, which could have added to the cost on the contractor side.

A bond package, presented to council for the first time Monday, preemptive­ly included another $2.4 million for the footbridge to make up the gap to pursue the project to its fullest if they chose to do so. The full $26 million bond package will be up for approval June 10 which will make the Jefferson Avenue Footbridge project fully funded.

At the community meeting, city staff said the project is expected to begin constructi­on in spring next year with completion targeted for fall 2025.

Marta Mieze covers local government at the News-Leader. Have feedback, tips or story ideas? Contact her at mmieze@news-leader.com.

 ?? ?? The Jefferson Avenue Footbridge on Oct. 10, 2023. The footbridge has been closed since spring of 2016 after a routine inspection discovered corrosion that presented safety concerns.
The Jefferson Avenue Footbridge on Oct. 10, 2023. The footbridge has been closed since spring of 2016 after a routine inspection discovered corrosion that presented safety concerns.

Newspapers in English

Newspapers from United States