Northeaste­rn schools report solid progress on constructi­on sites

Northeaste­rn campus to open in fall; Kenton Ridge eyed for 2023.

- By Brooke Spurlock Staff Writer BILL LACKEY / STAFF Contact this reporter at 937-6107310 or email brooke.spurlock@coxinc.com.

School constructi­on projects in the Northeaste­rn Local Schools continue to progress, the district’s superinten­dent says.

The district is building new campuses for Northeaste­rn and Kenton Ridge, spending $42 million on the Northeaste­rn site and $57 million on the Kenton Ridge building. The Northeaste­rn site is expected to open this fall and the Kenton Ridge site is anticipate­d to open in 2023.

Superinten­dent John Kronour said constructi­on at the Northeaste­rn site has “really ramped up and is progressin­g quickly.”

A lot has been happening inside the building, Kronour said, including windows installed, primer and the first coat of paint up on most of the walls and cabinets and floors installed.

“Ahead of the holiday break, prep work for the terrazzo flooring in the main commons area outside of the high school gymnasium and theater was underway, and the media center was starting to get framed out,” Kronour said.

At the Kenton Ridge site, constructi­on is “well underway.”

“The concrete slabs have been poured, gas lines installed, metal framing has gone up, and most of the work is taking place inside the facility,” Kronour said. “The exterior brick veneer continues to be installed along the north wall area, which is the kitchen and food services area, student dining, stage and gymnasium.”

Kronour added that both the interior and exterior masonry walls have been completed in various areas throughout the building, and a pitched roof structure has been installed on the third floor.

One of the new buildings will be located on the northeaste­rn side of the district, adjacent to the South Vienna school, and the other building will be on the property near the Kenton Ridge side.

The constructi­on projects are roughly $4 million under budget. The extra funds can be used toward additional projects to the buildings once they are complete.

Voters approved a 37-year, $79 million bond issue for two new Prek-12 facilities in May 2018. In addition, the state will contribute 40%, or $40 million, to the project through the Ohio Facilities Constructi­on Commission, bringing the total cost of the two schools to nearly $120 million.

One of the new buildings will be located on the northeaste­rn side of the district, adjacent to the South Vienna school, and the other building will be on the property near the Kenton Ridge side.

 ?? ?? Work has “really ramped up” at the Northeaste­rn Local Schools campus in South Vienna.
Work has “really ramped up” at the Northeaste­rn Local Schools campus in South Vienna.
 ?? BILL LACKEY / STAFF ?? The new Northeaste­rn School under constructi­on is seen through playground equipment at South Vienna Elementary.
BILL LACKEY / STAFF The new Northeaste­rn School under constructi­on is seen through playground equipment at South Vienna Elementary.

Newspapers in English

Newspapers from United States