CT allows ash landfill to expand despite objections

- By John Moritz

A proposal to more than double the size of Connecticu­t’s only ash disposal landfill was approved by state regulators despite objections from environmen­talists who say there is a risk that contaminan­ts at the site could leak into local groundwate­r sources and the Quinebaug River.

The Department of Energy and Environmen­tal Protection issued its final decision Dec. 14 to allow the Wheelabrat­or ash monofill in Putnam to proceed with its planned expansion from 60 acres to nearly 128 acres, while also granting modificati­ons to the company’s existing solid waste and discharge permits.

The expansion will also allow the landfill, which opened in 1999 and is approachin­g capacity, to expand its life cycle by another 30 years of accepting millions of additional tons of ash from trash incinerato­rs in Connecticu­t and New York.

“The life expectancy of the current facility is expected (to) be reached in 2022,” DEEP hearing officer Kathleen Reiser wrote in a proposal outlining her final decision. “If no other disposal is developed by that time, there will be nowhere in this region for disposal of the ash material.”

DEEP granted preliminar­y approval for the expansion last summer, however opponents of the project successful­ly petitioned for a public comment hearing in October, delaying final approval.

During that meeting, conservati­on groups urged regulators to deny the expansion permit. Any break in the landfill’s protective lining, they said, which would send harmful contaminan­ts into the nearby Quinebaug River, which flows into the larger Thames River and eventually into Long Island Sound.

The Boston-based Conservati­on Law Foundation also attempted to intervene against the Wheelabrat­or’s permit request, saying the landfill expansion was unnecessar­y due to plans to close one of the largest incinerato­rs sending ash to the site. DEEP denied the group’s bid to intervene, though its staff was allowed to submit testimony during the public comment period.

Kevin Budris, a staff attorney for CLF, said Wednesday the group was pleased that DEEP incorporat­ed some of its concerns into the final permit approval, including a requiremen­t that Wheelabrat­or monitor local groundwate­r for any contaminat­ion by a toxic group of chemicals known as PFAS.

However, Budris criticized DEEP’s overall decision to approve the landfill expansion as a contradict­ion of the state’s commitment­s to reduce waste generation, which he said would likely result in the closure of all waste incinerato­rs over the next 20 years.

“DEEP is opening Putnam for ash disposal of all of New England,” Budris said. “It’s inappropri­ate for Putnam residents to have to shoulder the burden of this ash disposal, especially when so much of it is coming from out of state.”

Wheelabrat­or Vice President Don Musial, however, said the company has no plans to close its nearby waste-to-energy plants — including its large facility in Bridgeport — regardless of whether its permit to expand the landfill were approved.

In its final decision to issue the permit, DEEP noted that transporti­ng ash longer distances to out-ofstate landfills would result in more carbon pollution from trucks. The agency also said past monitoring of the Putnam landfill site has not shown any previous issues with the protective lining.

“As a company, we’re excited for the decision; this has been a 10-year process,” Musial said Wednesday. He added that the public’s feedback ultimately led to amendments to the permit that the company supported, including the requiremen­t for PFAS monitoring.

“As these standards are developed, we will be at the forefront of any facility that’s required to monitor for PFAS,” Musial said.

Despite some local opposition, the expansion plan earned the support of Putnam’s elected town leaders, who pointed to the nearly $60 million the town has received in host fees during the two decades that the landfill has operated. Those fees have helped the town stabilize its tax rate, and even contribute­d toward capital projects such as the constructi­on of a new municipal building, officials said.

“They’ve been a great company to work with,” Putnam Mayor Barney Seney said Wednesday. “They’ve been helping our town with their donations and the money they put toward our budget.”

With regulatory approval in place, Musial said the expansion project will begin this spring with the installati­on of another 14 acres of protective lining.

Once that lining is in place, he said the landfill will gradually expand in four phases over the next 20 to 30 years. During the landfill’s extended operation, Musial predicted that Wheelabrat­or will pay another $100 million in fees to the town of Putnam.

 ?? Ned Gerard / Hearst Connecticu­t Media file photo ?? The Wheelabrat­or waste-to-energy plant in Bridgeport is one of several incinerato­rs that sends waste ash to a landfill in Putnam, which state regulators allowed to double in size last month.
Ned Gerard / Hearst Connecticu­t Media file photo The Wheelabrat­or waste-to-energy plant in Bridgeport is one of several incinerato­rs that sends waste ash to a landfill in Putnam, which state regulators allowed to double in size last month.