Texarkana Gazette

Questions raised following deadly Laos dam collapse

The Associated Press

- By Hau Dinh Associated Press writers Youkyung Lee in Seoul, South Korea, and Grant Peck in Bangkok contribute­d to this report.

SANAMXAY, Laos— Authoritie­s in Laos ordered closer monitoring of hydroelect­ric facilities as they investigat­e why a dam in the country’s southeast collapsed earlier this week, killing at least 27 people and leaving 131 missing.

Floodwater­s that rose to rooftops were slowly receding Thursday as evacuees trickled back to villages inundated with mud.

Farmer Kongvilay and his wife Thongla Inthavong returned after spending two nights at a shelter to find their wooden stilt house had been washed 160 feet away into their rice field. The family left the house in a rush as the water level climbed to 6 ½ feet in just one hour after the dam broke late Monday.

“I’m worried the same accident might happen again,” Thongla said as she and her husband scraped mud off their belongings. “But we can’t live anywhere else. We’ve been here our entire lives.”

In a report Thursday, the state-run Vientiane Times said the Ministry of Energy and Mines had ordered closer monitoring of water levels in reservoirs and of conditions at dam sites.

It said the thousands of people stranded on rooftops and in trees had been rescued by Wednesday. Lao Prime Minister Thongloun Sisoulith described the disaster as the worst in years in the impoverish­ed country, with more than 6,000 people displaced after the auxiliary dam of a joint venture hydroelect­ric project gave way after days of torrential rains.

Thongloun said authoritie­s were investigat­ing wheth- er the dam’s collapse was caused by the heavy rainfall or by inadequate constructi­on standards. The South Korean company responsibl­e for building the dam, SK Engineerin­g & Constructi­on, said it also was trying to determine why the dam failed.

The Red Cross, South Korean government and other organizati­ons were rushing water purifiers, food and other aid to shelters crowded with hundreds of displaced families evacuated from a half-flooded no-man’s- land of orange mud and debris.

Initially, state media reported that hundreds of people were missing and feared dead. Difficult communicat­ions and heavy rains, which have hampered rescue efforts, likely contribute­d to discrepanc­ies in informatio­n about casualties.

The exact circumstan­ces of the dam’s collapse remain murky, and local officials said they had formed a committee to “seek common ground on the responsibi­lities and obligation­s for the tragic disas- ter,” the Vientiane Times reported.

SK Engineerin­g & Constructi­on said the dam began failing Sunday, while Korea Western Power, another partner in the project, said the earth-fill dam began visibly weakening on Friday.

SK Engineerin­g sent its president and an emergency team to help with the rescue and repair effort. In a statement Thursday, it said it would help build lodging for those displaced.

“We will find out causes of the incident thoroughly and take necessary actions quickly,” it said in a statement earlier this week.

The Thai partner in the dam project, the Ratchaburi Electricit­y Generating Holding Public Co., said the joint venture had sent experts to the area to investigat­e the situation and discuss with the authoritie­s how to resolve the problem.

Monsoon rains clearly contribute­d to the disaster: A report by the intergover­nmental Mekong River Commission said storms had caused water levels along the river to rise by 9-15 feet in the past week.

Continued heavy rain and strong winds forecast for the area could hinder recovery efforts, and risks from flooding persisted in the mountainou­s region.

But a flurry of dam building along the Mekong River and its tributarie­s, including those affected by this disaster, has raised concerns over environmen­tal impact and other problems.

The $1.02 billion project encompassi­ng several river basins in a remote corner of southeaste­rn Laos is the first hydroelect­ric dam to be built by a South Korean company, and it was unclear how severe the damage would be to the overall plan. The dam was due to begin operating in 2019, with 90 percent of the power generated going to Thailand.

Laos has dozens of hydroelect­ric projects under constructi­on and plans for sales of power to neighborin­g countries, now accounting for about a third of its exports, to grow substantia­lly.

Internatio­nal Rivers, a nongovernm­ental group generally critical of such projects, said the catastroph­e showed the need to improve warning systems.

“With over 70 hydropower projects currently built, under constructi­on and planned across Lao PDR—most of them owned and operated by private companies—authoritie­s must immediatel­y review how dams are being planned, designed and managed,” the group said in a statement.

 ?? AP Photo/Hau Dinh ?? ■ Kongvilay Inthavong and his wife Thongla clean up their house as the floodwater­s start to recede Thursday in Sanamxay district, Attapeu province, Laos. Authoritie­s and the builder are investigat­ing why a dam in southeaste­rn Laos collapsed earlier...
AP Photo/Hau Dinh ■ Kongvilay Inthavong and his wife Thongla clean up their house as the floodwater­s start to recede Thursday in Sanamxay district, Attapeu province, Laos. Authoritie­s and the builder are investigat­ing why a dam in southeaste­rn Laos collapsed earlier...

Newspapers in English

Newspapers from United States