The Atlanta Journal-Constitution

Stormwater project around the corner

- BILL BANKS FOR THE AJC

Decatur’s commission recently approved design services for downtown stormwater improvemen­ts to commence in late spring. Total cost is $1.25 million for 1,200 linear feet of pipe running from East Trinity Place at the fire station, extending east along East Howard Avenue and turning north on Barry Street.

A branch is also planned from East Howard, connecting with an existing line crossing North Candler Street. Work will take roughly one year. This will complete Decatur’s major stormwater improvemen­ts that began in 2007 when a new line was built under Decatur High’s football field.