Ca­toosa County was able to close the fi­nan­cial books on ren­o­va­tion of Fire Sta­tion 3 on U.S. High­way 41 in early Oc­to­ber when the project was fin­ished a few thou­sand dol­lars un­der bud­get.

Ac­cord­ing to Chief Randy Camp, the over­all ren­o­va­tion came in al­most $4,000 un­der bud­get.

The Board of Com­mis­sion­ers unan­i­mously ap­proved a change or­der for the work dur­ing its Oct. 2 meeting.

“The change or­der is to Cha­zler Inc. for the Sta­tion 3 re­build and for the cer­tifi­cate of sub­stan­tial com­ple­tion of the project,” Camp said. “The orig­i­nal con­tract was ap­proved by com­mis­sion­ers for $722,206 and the com­ple­tion, which I’m