The Columbus Dispatch

Honey Creek Wind now expected to include about 60 turbines in Crawford

- Gere Goble

OCEOLA – The company working to develop the Honey Creek Wind Farm now expects to file its permit applicatio­n with the Ohio Power Siting Board for a 300-megawatt project in the middle of 2022, a spokeswoma­n said.

Previously, company officials had said they hoped to reach that stage by the end of this year.

During a “Conversati­ons on Wind” meeting Wednesday night at the Tod Township House, Carmen O'keefe, developmen­t manager for the project for Apex Clean Energy, explained the company's goal is now to get its permit in 2023, with commercial operation beginning in 2024. She estimated the “very large project” will include approximat­ely 60 turbines, each with an anticipate­d height between 590 and 670 feet.

Originally, Apex had planned a 360megawat­t project in northern Crawford and southern Seneca counties, but the project area no longer includes the latter county.

“The project has evolved over the past year or so, so now it is primarily northern Crawford, so anything north of (U.S.) 30, we are interested in,” O'keefe said.

A person in the audience asked why. “We don't anticipate them approving turbines there,” O'keefe said of Seneca County.

Tyler Fehrman, Apex's field manager for Ohio, elaborated on that statement.

“There are a group of individual­s who did not want it there,” he said. “Those individual­s happen to be probably a majority in Seneca County and thus the county's not going to approve the turbines. But there's another half of ‘they' in Seneca and in Crawford. So there's always going to be folks who are opposed; we understand that. But there also are landowners who would like to benefit from what this project has to offer.”

Developers are considerin­g extending the project into a small area in Wyandot County, O'keefe said. “We're still trying to see the viability of that.”

The power generated will feed into the regional transmissi­on grid. The plan is to connect to transmissi­on lines near Melmore in Seneca County.

Timeline for project uncertain

O'keefe, who took over the position with Apex previously held by Ben Yazman, said it's difficult to estimate how long it will take the Ohio Power Siting Board to rule on the permit request.

“It really varies on how long it takes from project to project,” she said. “I had one get permitted in seven months; I don't think this one would. Usually the wind projects take a few years ... it really will depend on who intervenes, what goes on in the hearings and all that.”

The company now has five temporary meteorolog­ical towers installed, and has completed some of the required environmen­tal studies. Its goal is to complete those studies, including wetland delineatio­n, this fall and in the spring.

Logistical­ly, Crawford County is a “really good site for wind,” and there has been a lot of interest from landowners, O'keefe said. “There's a lot of good, open land, even with the Ohio setbacks, that works.”

Fehrman, who grew up in nearby Knox County, said he originally was surprised to hear the company was planning a wind farm in Crawford

County.

“I was like, I've been to Crawford County; it's not that windy. We're not talking about wind like you and I feel it when we're walking outside,” he said. “There are meteorolog­ical patterns and maps that we don't feel, but we can observe. And so this area is part of that weird snow belt that we get in Ohio ... the wind blows far above where you and I are walking everyday. And the wind resource available in Crawford County is incredible. It's stronger than a lot of areas.”

The fact that Crawford County's commission­ers have designated it an Alternativ­e Energy Zone, or AEZ, also makes it attractive to the company for developmen­t, O'keefe said. That designatio­n means instead of paying property taxes on the developmen­t, the company will be pay PILOT (Payment in Lieu of Taxes) fees of $9,000 per megawatt, nameplate capacity, each year. The project is expected to bring roughly $2.7 million into the county each year that it's in operation.

How Ohio regulation­s will shape project

O'keefe also outlined some of Ohio's regulation­s for wind farm developmen­ts, which she described as being among the most stringent in the country:

• The formula for how close a turbine can be placed to a property not participat­ing in the project is based on the length of the turbine's blade, plus 1,125 feet. For the size of turbines Apex anticipate using in the project, that works out to about 1,375 feet from the property line.

• Sound studies, which already have begun, calculate the nighttime ambient sound level across the project area. The noise level at nonpartici­pating homes cannot exceed that average plus 5 decibels. Sound monitoring was done near both busy roads and rural areas, O'keefe said.

• If shadow flicker – the effect caused when a turbine blade passes between a residence and the sun – exceeds 30 hours per year, the company must take actions to curtail its effects.

• Before constructi­on begins, the company must file a final decommissi­oning plan with the power siting board, and a bond to cover the estimated cost is held by the board.

“So if something goes wrong, it's in their hands to take it down,” O'keefe said.

She also noted that each turbine takes up about a half-acre of land, including an access road. “Farmers do farm right up to them,” she said.

Ares acquires a majority stake in Apex

Apex is a privately owned renewable energy company based in Charlottes­ville, Virginia, with many projects across the country

On Oct. 6, Apex and Ares Management Corporatio­n announced that the latter had agreed to acquire a majority stake in Apex, providing that company with additional equity growth capital, according to a company news release.

In the past, Apex sold some of the projects it developed, including the Isabella Wind project in central Michigan, which company representa­tives have in the past described as comparable to what's planned with Honey Creek.

The new agreement with Ares means Apex won't have to do that as often, Fehrman said. ggoble@gannett.com 419-521-7263

Newspapers in English

Newspapers from United States