The Day

Contractor sues project manager over unpaid work on State Pier demolition

Branford firm says it is owed more than $800,000

- By GREG SMITH Day Staff Writer

Among other allegation­s, Blakeslee Arpaia Chapman alleges a breach of contract and breach of the “implied covenant of good faith and fair dealing,” a violation of the Connecticu­t Unfair Trade Practices Act, and also “unjust enrichment” on the part of the Connecticu­t Port Authority.

A Branford-based engineerin­g and constructi­on company contracted to perform work at State Pier in New London has filed a lawsuit claiming it is owed more than $800,000 for extra work it performed during the demolition stage of the massive rehab project.

Blakeslee Arpaia Chapman Inc. filed the suit in November against Kiewit Infrastruc­ture Co., the project manager of the $255.5 million State Pier project being overseen by the Connecticu­t Port Authority.

Both the port authority and Travelers Casualty and Surety Co. of America, the company that held the bond that assures all entities involved with the project will be paid, are named in the suit.

Kiewit disputes the claims in legal filings related to the case, which is pending in New London Superior Court.

Kiewit subcontrac­ted Blakeslee in March 2021 to perform work demolishin­g clusters of concrete mooring blocks atop piles, called dolphin moorings. The work is part of a re-imagining of State Pier into a staging and assembly area for offshore wind farms.

Kiewit agreed to pay $1.877 million to Blakeslee for the work but, the suit alleges, refused to pay Blakeslee another $838,422 it requested. The additional money includes $763,497 requested for extra work and $79,925 in retainage, a withheld portion of a final payment.

Blakeslee argues in the suit that an underwater inspection of the work to be performed revealed that the underwater piles that were to be removed had been spliced together, “not structural­ly sound because of improper design, poor constructi­on, and/or extensive corrosion.” Blakeslee notified Kiewit, the suit claims, that it should expect increased costs for the removal.

“Thus, when Blakeslee began the work on the Connecticu­t State Pier, it encountere­d site conditions differing materially from those represente­d in the contract and bid documents, plans, specificat­ion, and drawings, and it was required to do unforeseen and unanticipa­ted extra work directed by the defendant

Kiewit that was necessary for the completion of the Subcontrac­t,” the suit alleges.

Blakeslee said it had informed Kiewit of its modified plan, which involved removing concrete and pulling up piles from the water from a crane atop a barge. The pile splices repeatedly broke when being pulled and Blakeslee was forced to use divers, the suit claims. Of the 104 foundation mooring piles, 60 had one or more failed splices that required extra work, “including diver extraction,” the suit alleges.

“Throughout the Project, Kiewit never instructed Blakeslee not to perform the extra work and indeed instructed and directed Blakeslee to continue its work, including the extra work, while the change order was pending,” the suit claims.

By October 2021, Kiewit informed Blakeslee that the port authority had authorized up to $385,000 for the extra work, which Blakeslee refused.

Among other allegation­s, Blakeslee alleges a breach of contract and breach of the “implied covenant of good faith and fair dealing,” a violation by Travelers of the Connecticu­t Unfair Trade Practices Act, and “unjust enrichment” on the part of the Connecticu­t Port Authority. The suit claims the port authority benefited from the extra work without having to pay for it.

Representa­tives from both Blakeslee and Kiewit declined to comment, citing the pending litigation. A representa­tive from the port authority did not return messages requesting comment.

The lawsuit was filed in November 2022, and the two sides have traded motions in New London Superior Court. Earlier this week, Kiewit filed a motion to move the case from New London Superior Court to the state’s complex litigation docket.

“This matter involves a highly technical subject matter of underwater pile extraction, means and methods of extraction, as well as complex dispute resolution process with the owner, The Port Authority on a constructi­on project in excess of $200 million,” the motion from Kiewit attorney Larry Grijalva reads.” Kiewit anticipate­s that this matter will involve numerous experts, consultant­s, and a cumbersome discovery process.”

Newspapers in English

Newspapers from United States