The Denver Post

Supreme Court hears battle over Atlantic Coast Pipeline

- By Denise Lavoie

The Supreme Court on Monday appeared ready to remove an obstacle to constructi­on of the Atlantic Coast Pipeline, with a majority of justices expressing skepticism about a lower court ruling that tossed out a key permit needed for the natural gas pipeline to cross under the Appalachia­n Trail.

Justices on the court grilled a lawyer for environmen­tal groups who sued and won a 2018 ruling from the Richmond-based 4th U.S. Circuit Court of Appeal throwing out a specialuse permit for the 605-mile natural gas pipeline.

The 4th Circuit found the U.S. Forest Service did not have the authority to grant a right-of-way to allow the pipeline to cross beneath the Appalachia­n Trail in the George Washington National Forest.

But conservati­ve justices, who hold a 5-4 majority on the Supreme Court, expressed reservatio­ns about the ruling, with Chief Justice John Roberts at one point saying the lower court’s finding would “erect an impermeabl­e barrier” to any pipeline from areas where natural gas is located to areas where it is needed.

“Absolutely incorrect,” attorney Michael Kellogg, representi­ng the environmen­tal groups, responded.

Kellogg said there are currently 55 pipelines that run under the Appalachia­n Trail, 19 of them on federal land with easements granted before the Appalachia­n Trail was designated as a national scenic trail under the 1968 National Trails System Act. The remaining pipelines are on state and private land, he said.

But Justice Brett Kavanaugh told Kellogg that the environmen­tal groups’ position has “significan­t consequenc­es to it, enormous consequenc­es.”

The 4th Circuit found that the 1920 Mineral Leasing Act allows rights-ofway for pipelines on federal land, except for land in the

National Park System. The court found that the trail is considered a unit of the National Park System, so the Forest Service doesn’t have the authority to approve a right-of-way.

Lawyers for project developers — Dominion Energy and Duke Energy — backed by the Trump administra­tion, say the Forest Service has jurisdicti­on over land in the George Washington National Forest, where a 0.1-mile segment of the pipeline would cross about 600 feet beneath the Appalachia­n Trail. The pipeline would bring natural gas from West Virginia to North Carolina and Virginia.

The Sierra Club and other environmen­tal groups say that because the 2,200mile scenic trail from Georgia to Maine is considered a unit of the National Park System, no federal agency can grant a right-of-way for the pipeline. They say only Congress can approve such a crossing.

Dominion and the federal government say the Trails

System Act did not transfer lands crossed by the trail to the National Park Service. They argue that although the Park Service is charged with overall administra­tion of the trail, the actual lands remain under the jurisdicti­on of the Forest Service.

The court’s liberal justices appeared skeptical of the argument that the trail cannot be considered “land” in the National Park System because it is only a right-of-way that crosses federal land under the jurisdicti­on of the Forest Service.

“It’s a ... difficult distinctio­n to wrap one’s head around,” Justice Elena Kagan said. “When you walk on the trail, when you bike on the trail, when you backpack on the trail, you’re backpackin­g and biking and walking on land, aren’t you?” Kagan asked Anthony Yang, assistant to the U.S. Solicitor General.

But the conservati­ve justices and Justice Stephen Breyer, considered to be a member of the court’s liberal wing, repeatedly noted that the pipeline will be buried more than 600 feet below the Appalachia­n Trail and so would not actually go across the trail.

Even if the court rules in favor of the project developers, the Forest Service would still need to address three other issues cited by the 4th Circuit when it tossed out the permit, including the court’s finding that the agency had failed to fully consider alternativ­e routes to avoid national forests.

Legal challenges brought by environmen­tal groups have prompted the dismissal or suspension of eight permits and halted constructi­on for more than a year. The project is now three years behind schedule and its original price tag has nearly doubled to $8 billion.

Newspapers in English

Newspapers from United States