The Denver Post

Vail urges CDOT to complete I-70 Vail Pass project as planned

- By Ali Longwell Vail Daily

As the Colorado Department of Transporta­tion rethinks the final stages of the I-70 West Vail Pass Auxiliary Lanes Project, the town of Vail is urging CDOT officials to complete two components of the project on the chopping block.

The two improvemen­ts in limbo include adding an auxiliary lane on eastbound I-70 before the “Narrows” section of the pass, which extends from mile marker 185 to the top of Vail Pass, and improvemen­ts to a westbound curve at mile marker 186.

In a letter to Gov. Jared Polis and Shoshana Lew, executive director of CDOT, the Town Council expressed “our strong concern and disappoint­ment with the significan­t change in scope of the West Vail Pass Project, particular­ly with the decision to remove the almost two-mile ‘Narrows’ portion of the eastbound auxiliary lane from the project.”

“Not completing the improvemen­ts through the Narrows as promised is shortsight­ed and a liability. A meaningful reduction in the number of incidents could be achieved with an auxiliary lane, thereby also reducing the number of I-70 closures,” the letter said.

The letter was written after leadership for the project received informatio­n from CDOT that these components would no longer be funded, according to the town. Greg Hall, the town’s public works director, serves on the leadership team and told the council at its March 5, meeting that this was a “significan­t disappoint­ment.”

On March 11, CDOT held a meeting with the Vail Pass project team and local stakeholde­rs to share an update. According to a memo, the meeting was held as CDOT finalizes “plans for the 2024 constructi­on season on Vail Pass and is seeking input on final elements to award the final constructi­on package for the project.”

Constructi­on on the I-70 West Vail Pass Auxiliary Lanes project started in 2021 and is expected to continue through 2026. According to the project website, the goal of the work is to “improve safety and operations in both directions of the highway on West Vail Pass,” including lane and infrastruc­ture improvemen­ts, relocation of the Vail Pass Recreation Trail, reconstruc­tion of two bridges and more.

Rising costs

CDOT is rethinking the scope as the cost of the project has more than doubled since it started. Initially, the work was projected to cost around $140 million. However, according to the memo from Monday’s meeting, the total project budget has grown to $325 million.

“To date, CDOT has added $89 million worth of additional infrastruc­ture improvemen­ts beyond what was first proposed in 2019,” the memo said.

The infrastruc­ture improvemen­ts include a new westbound bridge, hazmat collection systems for the new runaway truck ramp, fiber-optic cable replacemen­t, culvert remediatio­n, camera installati­ons, an avalanche mitigation system and more.

In addition, “CDOT has added $95 million from various funding sources to account for the acute inflationa­ry pressures that have hit the constructi­on industry since the scope and budget for this project was first establishe­d,” the memo adds.

Reshaping the project

With costs ballooning, CDOT’S “preferred option” for the remaining work on the project would deliver “as many project elements as possible with remaining funding,” while leaving some elements “for future constructi­on that can be completed without larger disruption­s or wasteful demolition of recent work.”

Matt Inzeo, communicat­ions director for CDOT, said that the recommende­d path forward has not been finalized and the project team has committed to further discussion on the scope of the work. However, decisions are expected to be made relatively quickly “to get plans set in a way that lets us make the most use of the limited constructi­on window each season.”

In the preferred option, the “critical features” that would be completed would include wildlife crossings and fencing, straighten­ing the westbound curve at mile marker 188, and constructi­ng 3.5 miles of an auxiliary eastbound lane from mile marker 187.3 to the top of Vail Pass.

Among the items that would then be left to a future date would include several pull-out areas, variable speed limit and variable message signs, improvemen­ts to the westbound curve at mile marker 186, and a 1.8-mile stretch of the planned eastbound auxiliary lane.

Vail responds

The latter two components are the ones that the town is advocating be left within the project scope.

“Not completing it will be considered a failure on the part of CDOT and will further erode the trust and confidence in CDOT and the state regarding the agreements made as part of the I-70 PEIS (Programmat­ic Environmen­tal Impact Statement),” reads the letter.

In listing why this portion of the project is so necessary, the letter emphasizes that the Narrows portion sees many incidents during the summer and winter because of large speed differenti­als, the area’s high snowfall and its steep grade.

The letter adds that eastbound Vail Pass “experience­s the most pass closures of any portion of the I-70 corridor,” which have a significan­t impact on the town of Vail and public safety staff.

“Vail Fire and Emergency staff responds to all emergency incidents on the pass, resulting in crews dangerousl­y exposed to moving traffic or forcing the lanes to be closed for emergency vehicles to respond. The auxiliary lane in many cases would allow issues being attended to while the traveling public could safely bypass the incident,” the letter said.

The letter acknowledg­es the budget shortfall of the project, but adds that these costs will only continue to increase and make “a future project unattainab­le.”

“We appreciate all the additional resources CDOT has put forward to move this challengin­g project to the point it is at. However, it is extremely short-sighted to not fund the final portion of completing the climbing lanes in the Narrows section as well as reducing a top accident location WB. The cost of this work will not get any cheaper,” the letter said.

Last week, in a meeting with Western Slope legislator­s, Sen. Dylan Roberts and Rep. Megan Lukens, the Vail Town Council raised its concerns over these elements being possibly eliminated from the project.

Newspapers in English

Newspapers from United States