The Macomb Daily

Pipe work in sinkhole aftermath continues

-

Macomb County Public Works this summer will begin work on a $13.5 million project to upgrade sewer lines in southern Clinton Township to help avoid a repeat of the 2016 collapse that caused the Fraser sinkhole.

A Public Works contractor will reinforce more than a half-mile of the Macomb Intercepto­r in the area of 15 Mile and Garfield roads west of the former sinkhole in the project known as “Segment 6” that will begin later this summer, with an expected groundbrea­king in August, according to county Public Works officials.

Public Works Commission­er Candice Miller said in a news release the project is necessary to ensure the pipes function over the coming decades.

“We must invest in and maintain our undergroun­d infrastruc­ture,” Miller said. “We cannot afford another sinkhole or sewer collapse. These repairs will take us into the next generation and beyond.”

The Macomb Intercepto­r carries the sewage flushed by more than 600,000 people in the 11 communitie­s that comprise the Macomb Intercepto­r Drainage District.

The project, awarded to Ric-Man Constructi­on of Sterling Heights, will cost less than expected as all three bids were lower than projected costs, Miller said.

“Among the three companies that bid on this project, I’m delighted that the lowest and qualified bid was from a local firm and at a significan­tly lower amount than engineerin­g estimates,” said Miller, who chairs the MIDD board.

Some of the funds may come from water-and-sewer rate payers in the 11 communitie­s but those rates are not expected to increase due to the project, officials said. MIDD municipali­ties include Fraser, Sterling Heights, Utica, New Haven and Clinton, Chesterfie­ld, Harrison, Macomb, Lenox, Shelby and Washington townships.

“It is our expectatio­n we will not have to raise rates on our rate payers,” Miller said in a video describing the project.

The county Board of Commission­ers last month approved a resolution to back the full faith and credit of the county for up to nearly $30 million in bonds for the project but the amount of the issue likely will be less than half that.

The MIDD’s collection of $12.5 million from a lawsuit over the sinkhole is being used for the ongoing, $28-million “Segment 5” project in the area of 15 Mile and Schoenherr roads, west of the Segment 6 project. That has freed up some funds to help pay for Segment 6, officials said.

In addition, Public Works may receive federal dollars from the infrastruc­ture stimulus program recently announced by President Biden, Public Works spokesman Norb Franz said.

Segment 6 will include some traffic lane closures but the road should remain open to traffic during the project, which is tentativel­y scheduled to start in August and completed in 2023. Segment 5 is scheduled for completion next year.

Officials said Segment 6 will include the lining of approximat­ely 2,100 feet of the 5-foot diameter pipe along 15 Mile, east of Garfield, plus a new access shaft at the eastern end of the project.

That will be followed by the lining of a 1,200-foot curved portion of the 11-foot diameter intercepto­r at the intersecti­on.

Additional­ly, an “air jumper” will be installed and connected to the existing bio-filter on 15 Mile to help alleviate odors that have been prevalent in the area for many years, officials said.

“It will hopefully eliminate, certainly will help in a huge way, all of the different sewer odors people have been complainin­g about in this region for a very long time,” Miller said.

The collapse that caused the Fraser sinkhole on 15 Mile between Utica and Hayes roads was one of the worst infrastruc­ture failures in Michigan history, costing $75 million to repair it. The massive sewer collapse occurred 65 feet below the surface and forced the evacuation of 23 homes, including three that were condemned, two of which were eventually demolished.

Miller took office Jan. 1, 2017, days after the collapse and oversaw the excavation of a trench on 15 Mile the size of a football field, and the installati­on of a new, 11-foot diameter sewer line. The project was completed in less than a year.

A lawsuit filed by the MIDD over the project resulted in the $12.5 million settlement with three contractor­s working on the Oakland-Macomb Intercepto­r.

Miller ordered inspection­s of other parts of the intercepto­r.

They revealed significan­t corrosion of stretches that have reinforced concrete pipe, including exposure of steel rods, officials said. Extensive grouting was completed in the sewer beneath 15 Mile Road.

The Segment 5 project, which began last fall, involves contractor­s digging a massive 65-foot-deep shaft in the ITC corridor where workers will enter the massive sewer and install glass fiber polymer pipe to 7,000 feet of unreinforc­ed concrete.

Going east, 1,300 feet of 8-foot diameter pipe will be spray-lined with a geo-polymer coating.

“This type of rehab work is very important. Undergroun­d infrastruc­ture may be out of sight to many folks but it can’t be out of mind,” Miller said. “It’s like performing critical preventive maintenanc­e on your home in order to avoid major problems.”

In a related move, a contract was awarded last December for the inspection of 26 miles of pipe and 363 manholes that are under the jurisdicti­on of Public Works Office.

 ??  ??
 ??  ??
 ?? PHOTOS COURTESY OF MACOMB COUNTY PUBLIC WORKS ?? Crews in March work near a 65-foot-deep shaft off 15Mile Road west of Schoenherr in the ITC corridor that provides access to sewer lines that are being reinforced as part of the Segment 5project by the Macomb County Public Works Office. Work will begin late this summer to reline pipes in Segment 6, located east of Segment 5near 15Mile and Garfield Roads.
PHOTOS COURTESY OF MACOMB COUNTY PUBLIC WORKS Crews in March work near a 65-foot-deep shaft off 15Mile Road west of Schoenherr in the ITC corridor that provides access to sewer lines that are being reinforced as part of the Segment 5project by the Macomb County Public Works Office. Work will begin late this summer to reline pipes in Segment 6, located east of Segment 5near 15Mile and Garfield Roads.

Newspapers in English

Newspapers from United States