The Macomb Daily

Panel OKs revised add-ons for new Sheriff’s boathouse

- By Jameson Cook jcook@medianewsg­roup.com

About $130,000 for additional expenditur­es for the Macomb County Sheriff’s new boathouse were approved Tuesday by a committee of the county Board of Commission­ers.

The commission’s Internal Services Committee gave the preliminar­y go ahead at its meeting in the Administra­tion Building in Mount Clemens for the county to spend $95,000 for the purchase of a water pump and switch county officials recently determined were needed more than halfway through the multi-million-dollar project because the existing watersuppl­y system for the firesuppre­ssion system was inadequate.

The board also approved $35,700 for the engineerin­g firm, Shelby Township-based Anderson, Eckstein & Westrick, to design the system to retrieve water from Lake St. Clair and pump it to the fire-suppressio­n system. Officials determined Harrison Township’s current water system couldn’t provide enough pressure for the system to automatica­lly respond to a fire.

The expenditur­es are related to the board late last month reversing its prior near-unanimous approval of $1.7 million in add-ons for the project, increasing the cost from $8.4 million to $10.1 million, and pushing back the completion date from July 1 to Sept. 1. Work began last spring.

Nine days earlier, the committee, which is composed of the entire board, approved spending amounts not to exceed $866,000 for the water-supply system, $791,000 for five boat hoists in the boat garage and $50,000 for a public-address system, upon request of Facilities and Operations Lynn Arnott-Bryks.

But commission­ers became concerned about approving the expenditur­es without bids and in a 11-0-1 vote remanded the items back to the committee and Arnott-Briks for better informatio­n. Commission­er Sylvia Grot of Shelby Township has abstained from all of the boathouse votes and both during roll call and after the meeting would not say why.

Arnott-Bryks apologized to commission­ers at Tuesday’s meeting for “all of the questions that went unanswered” at the full board meeting.

The panel OK’d the purchase of the water pump and switch from bidder Rockford Constructi­on, doing business as Tristar Fire Protection Inc., in Detroit. It will go to the full board March 16 for final approval.

The remainder of watersuppl­y system will include installati­on of a small pump house, installati­on of pipe into the ground to access lake water and installati­on of pipe from the pump to the boathouse. Bids will be sought later for those jobs. The pump and switch won’t be available for about four months due to the process of ordering and manufactur­e of the pump, and the engineerin­g firm must design the system.

For the boat hoists and public-address system, Arnott-Bryks is seeking cost estimates to bring back to the board.

Committee Chairman Don VanSyckel said after the meeting that despite the delays, he is “pleased” officials discovered the issues “now instead of later.”

“We have to make sure we have a good fire-suppressio­n system,” he said. “We’re trying to be good stewards.”

The fire-suppressio­n system inside the structure was already approved as part of the original project cost.

VanSyckel couldn’t say whether the new developmen­ts will delay the project completion longer than the two months revealed last month.

The project’s total cost also could rise due to it being extended, officials said.

Newspapers in English

Newspapers from United States