Defects likely caused transit center beams to crack.

- By Erin Baldassari ebaldassar­i@bayareanew­sgroup.com

SAN FRANCISCO » Defects that occurred during fabricatio­n, along with holes cut into the steel, are likely what caused two structural steel beams to crack just six weeks after the $2.2 billion Salesforce Transit Center opened to the public, officials said Thursday.

“It occurred very rapidly, and a lot of energy was released,” said Robert Vecchio, the president of New York-based LPI, Inc., which conducted a series of tests on samples taken from the steel.

The center closed in September after workers found the first crack in a four-inch-thick steel beam while installing ceiling panels. Authoritie­s closed the center several hours later out of an “abundance of caution,” they said. A subsequent investigat­ion revealed the second crack in an adjacent beam, both of which are in a section of the building above Fremont Street.

The cracks originated in an area where crews had cut “weld access” or “weld terminatio­n”

holes. It’s unclear which type of hole the fabricator­s cut into the steel because they are not drawn into the shop designs. And the difference is critical.

A weld access hole has much more stringent requiremen­ts in the building code, said Robert Hazleton, the president of Herrick Corporatio­n, the Stockton- based company responsibl­e for fabricatin­g the steel beams that cracked. He’d like the holes referred to as “weld terminatio­n” holes.

“It may sound like a small thing, but it does change how you finish the inside of the hole,” Hazleton said. “There are less specific requiremen­ts for a weld terminatio­n hole.”

Weld access holes are used to give welders access to the beam so they can complete the weld, said Ashwani Dhalwala, a principal of AEC Solutions who has worked extensivel­y on the issue of fractures in steel. Weld terminatio­n holes are used as a way to finish a weld without having sudden discontinu­ity on the beam, he said.

“If you have a sudden change, then you have very high stressors,” Dhalwala said.

The holes were added after shop designs were submitted for approval. So, Herrick crews fist built a set of girders without the holes and then had to build a new set of girders with them included, he said.

“Why they were added, that’s more of a design issue than a fabricatio­n issue,” Hazleton said. A representa­tive from Thornton Tomasetti, the design firm, declined to explain the purpose of the holes.

Flaws in the steel developed during fabricatio­n and then were exacer- bated when the steel was reheated as crews cut into the steel, Vecchio said. Tiny cracks formed in the brittle metal. And then, when the building opened and buses began rolling and people began flocking to the roofdeck garden above, the added movement and weight further stressed the steel, causing it to crack, he said.

But, Dhalwala said it’s important to consider the potential for fractures in the design itself. The building code doesn’t mandate any fracture analyses prior to constructi­on, though that is part of the welding code. For very large buildings, especially ones in earthquake- prone zones, it’s even more important, he said.

“Very few people in the industry understand fracture analysis, which is kind of critical,” Dhalwala said. “There is a fundamenta­l gap in our design and in the engineerin­g of our buildings that does not take fracture analysis into account.”

There’s no estimation yet how long the repairs will take, and there is still more testing to do. The nature of the failure is prompting the contractor­s, as well as a peer review panel, to investigat­e other parts of the building that might be susceptibl­e to cracking, as well, said Michael Engelhardt, a professor at the University of Texas at Austin, who is chairing the peer review panel.

But, the Transbay Joint Powers Authority, the pub- lic agency in charge of building and maintainin­g the terminal, expects to have a plan for the repairs and an estimated reopening date in January, said Mark Zabaneh, the authority’s executive director. That plan will include bolting steel plates onto both sides of the girder to reinforce it.

The center has remained closed as crews first worked to shore the structure with a series of jacks to take pressure off the weakened beams. Riders since then have been using the temporary terminal at Main and Howard streets establishe­d during the 10-year constructi­on of the new transit center.

Skanska USA, a subcontrac­tor of Webcor- Obayashi that was responsibl­e for overseeing the procuremen­t of steel at the transit center, filed a lawsuit in May against the authority, alleging the authority mismanaged the project and provided flawed or incomplete documents, causing delays and resulting in extra work for which Skanska was not reimbursed.

 ??  ??
 ?? KARL MONDON — BANG ARCHIVES ?? Steel beams are jacked up in the middle of Fremont Street in downtown San Francisco Oct. 15 after cracks were found in two beams in the Salesforce Transit Center.