The Mercury News

San Jose BART project needs transparen­cy

-

For nearly a year now, the Santa Clara Valley Transporta­tion Authority has known that the federal government has serious doubts about the cost estimates and timeline for a planned BART extension through San Jose.

VTA officials dismiss those concerns as worst-case scenarios. Nothing to see here. Move along, please.

That's simply unacceptab­le. Especially when the federal analysis, which VTA finally released this month, concludes that the transit agency's “highly aggressive” estimates understate the constructi­on time by four years and the cost by $2.2 billion.

The Bay Area has a long history of late and overbudget taxpayer-funded transporta­tion projects. There's now good reason to question whether the 6-mile BART extension from the Berryessa/North San Jose station through downtown to Santa Clara will become the latest example.

The extension is being built by VTA, which will pay maintenanc­e and operating costs to the Bay Area Rapid Transit District to run the trains. The extension was forecast in 2014 to be completed in 2026 at a cost of $4.7 billion. In 2020, VTA adjusted its projection­s to 2030 and $6.9 billion, respective­ly.

Then, as Bay Area News Group reporters Maggie Angst and Eliyahu Kamisher reported Friday, the newly released documents show the U.S. Federal Transporta­tion Administra­tion estimated in May 2021 that the project would likely take until 2034 and cost $9.1 billion.

That's eight years beyond the original estimate and nearly double the cost.

A key driver of cost and timetable uncertaint­y is the authority's decision to use a deep, single-bore tunneling method pioneered in Spain instead of convention­al dual bores. It was sold to the public as a way to minimize groundleve­l constructi­on that would disrupt downtown traffic and businesses and portrayed as a faster and less-costly alternativ­e, which are reasons we supported it.

But federal officials, while moving ahead with funding for the project, are now challengin­g VTA's time and cost estimates. Their concerns should be taken seriously — especially because the federal estimates raise questions about whether there's enough money for the project.

The VTA has already gone to voters twice — in 2000 and again in 2016 — with sales tax measures that together will fund about $4 billion of the extension. The federal government has agreed to fund 25% of the total cost, up to $2.3 billion. But if the federal government's cost estimates are right, funding for the project right now is nearly $3 billion short.

When VTA announced the Federal Transporta­tion Administra­tion funding in October, it didn't mention the agency's $9.1 billion cost estimate, nor the 2034 completion forecast.

It was the federal agency's announceme­nt the same day that revealed the cost forecast. And it wasn't until our reporters this month obtained the full federal report through a state Public Records Act request that the new date forecast for completion was learned.

VTA officials dispute the federal cost estimates and time projection­s. If they feel confident in their forecasts, then they shouldn't be afraid to subject both sets of numbers and time schedules to public scrutiny and seek an independen­t, outside opinion.

Voters and taxpayers deserve nothing less.

 ?? DOUG DURAN — STAFF ARCHIVES ?? The Bay Area has a long history of late and overbudget taxpayerfu­nded transporta­tion projects.
DOUG DURAN — STAFF ARCHIVES The Bay Area has a long history of late and overbudget taxpayerfu­nded transporta­tion projects.

Newspapers in English

Newspapers from United States