The Mercury News

San Jose BART extension plan needs scrutiny

- Daniel Borenstein is the editorial page editor. Reach him at dborenstei­n@ bayareanew­sgroup.com.

As the price for the South Bay BART extension continues to soar, elected officials must decide whether they want to honestly evaluate the project or rubber stamp it.

In just the last three years, the estimate for the four-station, mostly undergroun­d extension has more than doubled, from $5.6 billion to $12.8 billion, and the completion date has been kicked back more than a decade, from 2026 to 2037.

That's before a single shovel of dirt has been moved.

The rapid price escalation means the Santa Clara Valley Transporta­tion Authority — which is building the extension for BART to eventually operate — needs more federal tax money, which is not assured, and more county sales tax revenue, depriving other transporta­tion projects of funding.

At this point, VTA board members, a collection of elected officials from jurisdicti­ons throughout Santa Clara County, should be demanding a comprehens­ive, independen­t review of the six-mile extension from the existing Berryessa/North San Jose station through San Jose and up to Santa Clara.

That review should evaluate financial and ridership assumption­s in light of radically changed commute patterns since the COVID pandemic onset, the tunneling strategy that will require passengers descend eight stories undergroun­d to reach a boarding platform, and the planned final leg to Santa Clara that duplicates an existing Caltrain line.

Sadly, that review is not happening.

Instead, the board has appointed a subset of its members to serve on an oversight committee, which has done little so far.

VTA staff are talking about re-examining the costly tunneling plan. Tom Maguire, the recently hired chief megaprojec­ts delivery officer, said this week that someone from outside the agency will conduct the review.

But he could not say how independen­t that person would be. And he said no other issues would be considered. “We're committed to completing this project,” he said. In other words, full speed ahead.

Which is exactly the problem. Taxpayers deserve an independen­t and complete review — not cherry-picking topics and then putting a thumb on the scale.

Especially when we know that VTA staff cannot be trusted to be transparen­t. As VTA's own auditor noted in January, staff have been misleading the public and even their own board members. Indeed, the authority has a long record of public deceit.

If VTA board members want to regain public confidence, they will hire independen­t experts to examine the project's critical questions, of which there are at least three:

Financial projection­s

As we editoriali­zed last year, it's time for a fresh look at the financial and ridership projection­s and a comparison with alternativ­es that might provide mass transit or other environmen­tally friendly commuter options more cost-effectivel­y.

Perhaps the extension will still prove to be a wise investment. Or perhaps not. But with ballooning costs, so much taxpayer money at stake and the radical restructur­ing of commute and work patterns during the past four years, agency leaders should be asking whether the extension originally envisioned still makes sense.

Tunnel plan

For the approximat­ely five miles of tunneling, the transit agency has migrated from the twin-bore design to a single bore with platforms stacked one above the other, and then to a single bore containing the two tracks on the same level.

The transition has increased the size of the tunnels from 20 feet each in the twin-bore design to 53 feet in diameter for the most-recent option. The platforms, originally planned for 50 feet undergroun­d, are now expected to be 80 feet below the street. And the width of the platform was reduced from 28 feet to 22 feet.

The change to a single bore was to assuage concerns of business owners that downtown streets would be torn up with the shallower twin-bore constructi­on. VTA officials cling to that justificat­ion, but they have been unable to provide estimates of how much the single-bore tunneling adds to the total cost.

Some experts say concerns about disruption from the twin-bore plan were exaggerate­d, and switching to a single bore will drive up the cost and extend the constructi­on time. They also question whether alleviatin­g short-term constructi­on disruption justifies permanent longer escalators and more-crowded platforms.

Santa Clara leg

Respected public transit advocates complain that the extension's last leg — from Diridon Station in San Jose to Santa Clara — is duplicativ­e of parallel Caltrain service. And congressio­nal candidate and former San Jose Mayor Sam Liccardo, a big booster of the BART extension, in January called for at least temporaril­y dropping it.

Like for the tunneling question, VTA has been unable to — or refuses to — say how much the Santa Clara leg adds to the total cost.

As we editoriali­zed in 2021, 2022 and 2023, as costs kept rising and VTA transparen­cy remained abysmal, the BART extension should be subjected to complete and rigorous independen­t review.

Residents and taxpayers deserve an honest, impartial evaluation of its merits.

 ?? JOSE CARLOS FAJARDO STAFF PHOTOGRAPH­ER ?? In the last three years, the Santa Clara Valley Transporta­tion Authority's estimate for the fourstatio­n, mostly undergroun­d BART extension has more than doubled, from $5.6 billion to $12.8 billion, and the completion date has been kicked back more than a decade, from 2026 to 2037.
JOSE CARLOS FAJARDO STAFF PHOTOGRAPH­ER In the last three years, the Santa Clara Valley Transporta­tion Authority's estimate for the fourstatio­n, mostly undergroun­d BART extension has more than doubled, from $5.6 billion to $12.8 billion, and the completion date has been kicked back more than a decade, from 2026 to 2037.
 ?? ??

Newspapers in English

Newspapers from United States