The Middletown Press (Middletown, CT)

Merritt Parkway looking more brown than green?

- By Ben Lambert

NEW CANAAN — A stretch of brown landscape that should be green this time of year on the Merritt Parkway between New Canaan and Norwalk will improve after more constructi­on in the area wraps up, according to a conservanc­y group.

The constructi­on, which began this summer between Exit 37 in New Canaan and Exit 40A in Norwalk, includes safety improvemen­ts, bridge work and pavement reconstruc­tion, according to the state Department of Transporta­tion.

Officials with the Merritt Parkway Conservanc­y, a Stamfordba­sed nonprofit dedicated to stewardshi­p of the parkway, alerted residents to the work recently, as the shoulders of the road had prompted the removal of some mature trees.

“The roadside plantings look pretty bad right now,” Executive Director Wes Haynes said in a statement. “But when the project is finished and the new plants are in, we’ll have a better, safer parkway looking as beautiful as its designers first intended.”

Officials said new canopy and understory trees will be planted next year once the shoulder regrading work has been completed on the parkway, which is also known as Route 15.

“As guardians of the flora and aesthetics of the Parkway, the conservanc­y wants everyone to understand what’s happening,” said Haynes. “We have been working closely with Connecticu­t DOT and contractor­s on this project, so rest assured we’re looking out for the parkway’s future.”

He said he wanted to assure residents that “it’s not as bad as it looks.”

Shannon King, deputy communicat­ions manager with the Department of Transporta­tion, said in an email that planned safety improvemen­ts include adding four feet of pavement and a reinforced grass area to the roadway and replacing existing guide rails with steel-backed timber railing. There are also drainage improvemen­ts, including cross-slope correction­s and resurfacin­g, to “ensure the roadway remains in a state of good repair.”

“(C)oncrete curbs and gutters will also be installed to provide additional roadway drainage and outline the edge of the road,” said King. “Upcoming constructi­on work planned for the remainder of 2022 includes continued removal of invasive plant species, strategic clearing and thinning of roadside vegetation, and completing the initial roadway surface patching and resurfacin­g in preparatio­n for cross-slope correction­s.”

King noted that the department’s “landscape design team actively coordinate­s with various stakeholde­r groups” and maintenanc­e staffers on “strategic planting and clearing, resulting in more manageable and less frequent maintenanc­e.”

“CTDOT has been working collaborat­ively with partners like the Merritt Parkway Conservanc­y and will continue to do so through the completion of this project scheduled for fall 2024,” said King.

According to the DOT, workers have recently been clearing tree and brush impacted by the constructi­on recently between Exit 37 and 39A, beginning on the northbound side.

The $55 million project was awarded earlier this year to Yonkers Constructi­on. It is the last phase of an eight-part project begun 20 years ago to improve safety along the entire length of the Merritt. This phase is scheduled for completion in early 2024. It will widen the travel lanes eight feet in each direction with four feet of new paving bordered by four feet of stabilized shoulder for breakdowns.

Widening the roadway and shoulder requires the removal of some mature trees along the Merritt. The conservanc­y worked with the DOT to inspect the trees in the work zone and preserve the bucolic nature of the parkway.

Newspapers in English

Newspapers from United States