The News-Times

PHASE 4 STREETSCAP­E ENGINEERIN­G BID SELECTED

- — Currie.Engel@hearstmedi­act.com

The town has awarded the contract for engineerin­g services and designs for Phase 4 of the Streetscap­e Project to Freeman Companies.

The town is calling Freeman Companies the “most costeffect­ive qualified bidder” in the applicant pool.

The preliminar­y concept design plans have been posted online and the company’s designs are expected to be 30 percent complete by mid-July, at which time the town has said that they will schedule a public review of the work. The plan will consist of constructi­on of light fixtures, retaining walls, and over 1,900 feet of sidewalk from the northern end of Phase 1 constructi­on to the Newbury Village condominiu­ms on Federal Road.

At a special town meeting in February, the town inanimousl­y approved the $3.6 million needed for the fourth phase of the Streetscap­e Project.

Constructi­on is expected to start in the spring of 2023.