The News-Times

SCHOOL BUILDING PROJECTS ‘ON TIME AND ON BUDGET’

District: Progress on schedule despite COVID-based complicati­ons

- By Kendra Baker

NEW FAIRFIELD — Despite some supply chain problems resulting from the COVID-19 pandemic, the district’s two school building projects are moving along.

“Both the Consolidat­ed project and the high school project remain on time and on budget,” said the school district’s business and operations director, Rich Sanzo.

Funding for a $29.2 million Consolidat­ed Early Learning Academy and $84.2 million new high school were approved by taxpayers in October 2019, with some costs offset by state funding.

With constructi­on bids within the total allocated project budget, work on the learning academy broke ground in June and constructi­on on the high school commenced a few months later.

Although the constructi­on schedule for Consolidat­ed Early Learning Academy has been in flux, primarily due to supply chain delays, Sanzo said the town’s Permanent Building Committee and project team were recently able to secure roofing materials sooner than anticipate­d.

“As a result, the updated schedule is now projecting that Consolidat­ed will open on time,” he said.

The roughly 44,000-square-foot elementary school is expected to be finished by the start of the 2022-23 school year, and the 143,000 squarefoot new high school is slated to open the following year.

Although things are currently on track, Sanzo said supply chain constraint­s still pose “some risk” to the Consolidat­ed constructi­on schedule.

“We’ve talked to the (Permanent Building Committee) and the project team and they know that by the middle to end of January, we need to have full confidence in the opening

for the fall,” he said.

Not only are there school calendar implicatio­ns — whether schools will open before or after Labor Day next year — but budgetary and programmat­ic implicatio­ns as well, “as we look to plan for bringing two schools together on one campus,” Sanzo said.

Sanzo said the Permanent Building Committee is continuing to “work the schedule” to keep the project on track.

“Both the Consolidat­ed Early Learning Academy and New Fairfield High School building projects are progressin­g at a rapid pace,” Superinten­dent Pat Cosentino said in a Dec. 17 newsletter. “Anyone visiting our school campuses will notice that they are buzzing with activity on a daily basis with excavation, concrete pours, and steel erection taking place.”

With its steel superstruc­ture nearly complete, the outline of the Consolidat­ed Early Learning Academy can be seen at the Meeting House Hill School campus.

Preschool through fifth grade students and staff recently had the chance to leave their mark by signing a ceremonial beam that officially became part of the new elementary school during a steel-topping ceremony last Friday.

“High school and middle school students will have the same opportunit­y in the future when steel begins to be erected on the high school site,” Sanzo said.

Steel for the new high school is expected to arrive after winter break, according to Cosentino.

The original plan for the high school project changed last year after the town purchased a 2-acre property at 78 Gillotti Road, which allowed for what Permanent Building Committee member Anthony Yorio described as an “optimal building design” and more cost-efficient plan.

The town used $325,000 from its unappropri­ated capital and non-recurring account to acquire the property, and the Permanent Building Committee reduced the school’s constructi­on budget to offset the purchase.

With 78 Gillotti Road, the new high school will be constructe­d on a total of three parcels — the others being 54 and 74 Gillotti Road.

There have been some traffic pattern changes, but Sanzo said “internal school operations” at the high school have not been disrupted by constructi­on work. The new school is being built next door to the existing high school.

Not only will the new learning academy and high school address infrastruc­ture problems, Sanzo said, but they’ll create opportunit­ies to introduce educationa­l programs that the district hasn’t been able to have due to lack of space in its current facilities.

As constructi­on progresses on the new schools, Cosentino said teachers, students and administra­tors have been actively involved in the “furniture, fixture, and equipment phase” of the projects.

She said “traveling classrooms” have been set up inside the high school’s library learning commons to give staff and students the chance to try out learning environmen­ts, and the Consolidat­ed School cafeteria is currently filled with samples of early childhood furniture.

“Staff are meeting with the design team to articulate needs and explore ideas on how to best outfit instructio­nal spaces,” Cosentino said. “The feedback has been phenomenal with excitement growing for the opening of the new schools.”

 ?? New Fairfield Public Schools / Contribute­d photo ?? Aerial view of progress on the new Consolidat­ed Early Learning Academy site in New Fairfield.
New Fairfield Public Schools / Contribute­d photo Aerial view of progress on the new Consolidat­ed Early Learning Academy site in New Fairfield.
 ?? JCJ Architectu­re / Contribute­d photo ?? Conceptual rendering of the Consolidat­ed Early Learning Academy.
JCJ Architectu­re / Contribute­d photo Conceptual rendering of the Consolidat­ed Early Learning Academy.

Newspapers in English

Newspapers from United States