The Norwalk Hour

City set to pay $7.5M for utility work on Walk Bridge

- By Abigail Brone

NORWALK — The city is set to fund $7.5 million, paid in installmen­ts for the next three years, for utilities work associated with the Walk Bridge reconstruc­tion project.

The Common Council Public Works Committee approved the expense during a virtual meeting last week. The full council is set to vote on the issue at its Tuesday meeting

While constructi­on of the bridge and much of the project’s cost will be conducted by the state Department of Transporta­tion, the city will pay for various services including roadway sweeping and some engineerin­g and undergroun­d utility constructi­on, according to the agreement documents.

Norwalk’s portion of the cost will be paid in three installati­ons, one payment

for the next three years.

The first installmen­t is $3,750,000, which is to be paid to the DOT once the written acknowledg­ment of the project authorizat­ion is received. The second and third installati­ons — both $1,875,000 — will be due on July 1, 2022, and 2023, respective­ly, according to the documents.

Of the lump sum, $7 million is for the city’s portion of the constructi­on outlined in the agreement, while the remaining $500,000 will cover the DOT project inspection services.

“This is the first time the DOT, understand­ing the cap the city has on all capital projects, is helping us in dividing costs in three separate payments,” Norwalk Principal Engineer Vanessa Valadares said at Tuesday’s meeting. “It is really the first time the state is doing this. It shows a lot about the relationsh­ip we have been having between the Walk Bridge Program and DOT.”

Typically, the municipali­ty would have to agree to the payments in full for projects of this kind, Valadares said.

Public Works Committee Chair George Tsiranides agreed with Valadares regarding the unusual agreement.

“This is the first time I’ve seen a contract broken up over three payments,” Tsiranides said. “That’s wonderful they’re working with us in that particular way.”

With the agreement’s approval, a groundbrea­king is expected by the end of the summer, with paperwork and contractor­s finalized by late May, Valadares said. The entirety of the project, including the undergroun­d work for Norwalk the DOT has agreed to take on, should be completed in about two and a half years.

“This will be a big, big change to East Avenue,” Valadares said. “This will follow the bridge replacemen­t and widening of the road.”

Replacemen­t of the 124year-old bridge has been in the works since 2017. Prior to the pandemic, the 564foot-long bridge, which is part of Metro-North Railroad’s New Haven Line, transporte­d about 175 trains and 125,000 riders daily, according to the program website.

The cost difference between partnering with the DOT for the bridge constructi­on and having the city take on the project alone is minimal. But the joining allows the state to handle many of the coordinati­ng costs and leaves Norwalk to mainly pay for the utility work, Valadares said.

As part of the agreement, the DOT will be undergroun­ding utilities on East Avenue from Winfield Street to Fort Point Street, including overhead lines. The utility undergroun­ding is needed as part of the replacemen­t of the New Haven Line Railroad Bridge over East Avenue, according to the documents.

With unanimous approval from the Public Works Committee, the Common Council is set to vote on the Walk Bridge agreement at Tuesday’s meeting.

 ?? Erik Trautmann / Hearst Connecticu­t Media ?? The Metro-North Railroad Walk Bridge on Jan. 28 in Norwalk. Bridge replacemen­t operations will begin with a large dredging operation planned for the head of the Norwalk River.
Erik Trautmann / Hearst Connecticu­t Media The Metro-North Railroad Walk Bridge on Jan. 28 in Norwalk. Bridge replacemen­t operations will begin with a large dredging operation planned for the head of the Norwalk River.
 ?? Erik Trautmann / Hearst Connecticu­t Media ?? Workmen prepare to dredging for the Metro-North Railroad Walk Bridge Replacemen­t Project on Jan. 28 in Norwalk.
Erik Trautmann / Hearst Connecticu­t Media Workmen prepare to dredging for the Metro-North Railroad Walk Bridge Replacemen­t Project on Jan. 28 in Norwalk.

Newspapers in English

Newspapers from United States