The Oklahoman

Come together

- BY WILLIAM CRUM Staff Writer wcrum@oklahoman.com

With a final weld, nearly two years of streetcar constructi­on are rapidly coming to an end.

Workmen welded together the last two sections of rail for the Oklahoma City Streetcar on Wednesday afternoon, reaching a milestone on the way to beginning service in December.

Nearly two years of streetcar constructi­onrelated street closures and traffic disruption downtown are rapidly coming to an end.

Crews with contractor Herzog/Stacy & Witbeck have installed nearly six miles of track since constructi­on began in February 2017.

“It’s been a long time coming,” said MAPS 3 Program Manager David Todd.

The last weld was completed at NW 5 and Robinson Avenue, on a section called the 5th Street Turnback.

The one-block stretch of track gives operators flexibilit­y to keep streetcars moving through the central business district in the event service is disrupted or tracks are blocked in Midtown.

Some asphalt and concrete work remains on the NW 5 track bed but work is nearly complete.

“This is one more major crew that can leave town now and say their job is done,” Todd said.

Todd said the public can look for streetcars undergoing testing and operator training on the downtown loop over the next two months.

Testing began on the Bricktown loop in May.

The two loops comprise 6.9 miles of “service track.”

Riders will have connection­s to the Bricktown entertainm­ent district, the MAPS 3 convention center complex and park, central business district offices and shopping, and Midtown.

Routes reach from SW 3 on the south to NW 11 on the north, and generally from Hudson Avenue on the west to Broadway on the east. Streetcars will reach east to Joe Carter in Bricktown.

The city’s $4.5 million modern-design, low-floor streetcars are manufactur­ed in western Pennsylvan­ia by Brookville Equipment Corp. Seven were purchased.

 ??  ??
 ?? [PHOTO BY SARAH PHIPPS, THE OKLAHOMAN] ?? Edwin Abarca worked Wednesday at NW 5 and Robinson Avenue on the last weld on the nearly six miles of track installed downtown for the Oklahoma City Streetcar. More concrete is left to be poured on NW 5 but work is nearly complete, with streetcar service due to begin in midDecembe­r.
[PHOTO BY SARAH PHIPPS, THE OKLAHOMAN] Edwin Abarca worked Wednesday at NW 5 and Robinson Avenue on the last weld on the nearly six miles of track installed downtown for the Oklahoma City Streetcar. More concrete is left to be poured on NW 5 but work is nearly complete, with streetcar service due to begin in midDecembe­r.

Newspapers in English

Newspapers from United States