YPG’s Laguna Airfield undergoing expansion and improvemen­ts

- By Ana Henderson

With 2,000 square miles of restricted airspace, it’s safe to say, U.S. Army Yuma Proving Ground (YPG) sees a lot of air traffic.

That volume of activity causes degradatio­n on the runways.

“This used to have edge markings and it used to have a centerline and all sorts of markings,” pointed out Jim Walk, Laguna Airfield manager, as he points at the marks on the runway, “That was all rubber from the planes landing and you couldn’t even see the centerline, because it was obscured by the rubber.”

YPG supports the Airborne Test Force, Military Free Fall, Flight Detachment and Yuma Test Center’s Aviation Systems among various other developmen­tal and operationa­l testing.

To better serve those entities, Laguna Airfield is undergoing improvemen­ts. All the pavements are being resurfaced in one way depending on their needs. Cracks are being filled and fog sealed on the runways, taxiways, and aprons. A portion of a taxiway was milled and three inches of asphalt was applied. New markings will also be added.

In early February an additional runway, which had not been used for four years, is now back in service after flashing light were installed to warn vehicle traffic of an approachin­g aircraft. That runway was the first finished in January and the difference

is evident. The sleek black asphalt has pristine white markings.

Adding to these improvemen­ts, in December of 2021, the constructi­on of a hanger for the Flight Detachment got underway. It will include a new ramp and taxiway from the hanger to the runway.

With all the constructi­on taking place, Flight Services Division Chief

Patrick Franklin, commends those who are actively working behind the scenes to make it run smoothly.

“There’s a tremendous amount of coordinati­on going on to make sure that all the two different constructi­on contractor­s are talking to each other, DPW [Directorat­e of Public Works] and the Corps of Engineers are working closely together. We are working with the Mission folks to make sure all their imperative­s are still met.”

That involves weekly coordinati­on meetings that have been on-going since October.

Walk said, “We went from A, to B, to C, we had to keep something open all the time, we’re playing a shell game of keeping everything going.”

At times, contractor­s would stop constructi­on and move out of the way to allow missions to continue.

During constructi­on regular mission activities and largescale exercises including Project Convergenc­e Technology Gateway Demonstrat­ion, Weapons and

Tactics and Instructio­n course better known as WTI and other training and exercise activities proceeded uninterrup­ted.

The groundwork on the airfield is expected to be complete by April or May.

 ?? ?? In early February an additional runway, which had not been used for four years, is in service after flashing light were installed to warn vehicle traffic of an approachin­g aircraft. that runway was the first finished in January and now has sleek black asphalt and pristine white markings.
In early February an additional runway, which had not been used for four years, is in service after flashing light were installed to warn vehicle traffic of an approachin­g aircraft. that runway was the first finished in January and now has sleek black asphalt and pristine white markings.
 ?? ?? Laguna airfield is undergoing improvemen­ts. all the pavements are being resurfaced in one way depending on their needs. Cracks are being filled and fog sealed on the runways, taxiways, and aprons. (photos by ana Henderson)
Laguna airfield is undergoing improvemen­ts. all the pavements are being resurfaced in one way depending on their needs. Cracks are being filled and fog sealed on the runways, taxiways, and aprons. (photos by ana Henderson)
 ?? ?? In December of 2021, the constructi­on of a hangers for the Flight Detachment got underway. the project will include a new ramp and taxiway from the hanger to the runway.
In December of 2021, the constructi­on of a hangers for the Flight Detachment got underway. the project will include a new ramp and taxiway from the hanger to the runway.