The Palm Beach Post

As teams, contractor clash, work unfinished

Astros, Nationals want disputes over alleged ‘shoddy work’ ended.

- By Joe Capozzi Palm Beach Post Staff Writer

WEST PALM BEACH — When players and staff for the Houston Astros and Washington Nationals first arrived at the Ballpark of the Palm Beaches in February, they were asked to be patient: Their new $152 million shared spring training complex in West Palm Beach wasn’t quite finished.

What they may not have known was that a lot of the work hadn’t been done properly, the result of corners cut by work crews under extraordin­ary pressure to open on time, a Palm Beach Post review of internal emails, city inspection records and court documents found.

Although players and staff members never complained, at least not publicly, the shoddy work forced them to deal with a roster of minor inconvenie­nces: large buckets strategica­lly placed in the Astros clubhouse to collect water leaking from the newly installed roof and windows, pooling water from an improperly sloped shower, and ripples in the AstroTurf floor in the batting cages, to name a few.

In December, about two months before the first game, both teams briefly considered delaying the

ballpark’s opening until 2018 after West Palm Beach building inspectors flagged the concrete stadium seating bowl for failing to meet federal Americans with Disabiliti­es Act specificat­ions.

The ballpark wound up opening on time, with few, if any, visible signs of the hectic behind-the-scenes struggle to make that happen. And after more than 140,000 fans, many visiting from Houston and Washington, watched the ballpark’s Grapefruit League games, the teams went on to have successful seasons — the Astros won the World Series and the Nationals won a division title.

But with star players Jose Altuve, Bryce Harper and their teammates scheduled to return in three months, the ballpark still isn’t finished. And the county and teams are losing patience as the lead general contractor, a joint venture led by Hunt Constructi­on Group, scrambles to finish nearly $12 million in work.

That work includes repairs and remediatio­n on 23 so-called “non-conformanc­e” items that were done incorrectl­y or not according to the architect’s plans — from plugging roof leaks and replacing windows and drywall to fixing uneven floors and repainting areas that are rusting and flaking because the original applicatio­n did not include primer.

At the same time, Hunt is fighting with the teams and many of its 35 subcontrac­tors, some of them in court, over billing issues and delays that, according to Hunt, prompted some workers to walk off the job.

Now, it might be January before the city issues a final certificat­e of occupancy after having granted the teams a twice-extended temporary permit.

Get it done

To speed up completion, the Astros and Nationals in October started doing some work on their own, without using Hunt — from ceiling work in the Nationals’ executive offices to elevator finishes and repairs to the playing fields.

“We expected Hunt to be entirely completed with this project by now. You are not. Complete the project as contracted for. We have incurred enormous costs as a direct result,” Marc Taylor, the project manager for the teams, told Hunt in a Sept. 15 letter about a payment dispute.

In its reply, Hunt accused the teams of “placing the project in serious jeopardy with the subcontrac­tors” by delaying payments. The dispute is one of several that have dogged the project and created tension among the teams, the contractor and, at times, the county.

Hunt responded to questions with a short statement, issued to The Post through a public relations firm: “While the facility is already fully in use, the Hunt Straticon Messam Cooper joint venture has been meeting with the owners and is continuing to work with them to come to an agreement as quickly as possible on outstandin­g items.”

The teams certainly hope so.

“We expected some problems,” said Giles Kibbe, an Astros lawyer who has helped shepherd the project since its earliest days. “We had more than we expected, but we thought surely by now all of this would have been done and everyone would have been paid and we would all go our separate ways.”

Schedule ‘too tight’

Problems and delays are not uncommon in massive public projects involving dozens of subcontrac­tors. That was the case with the county’s $672 million waste-to-energy plant in 2015, the $127 million courthouse in 1995 and the $63 million Palm Beach Internatio­nal Airport terminal expansion in 1988.

At the ballpark, the pressure was on before work even started because of a protracted, politicall­y charged site selection process that dragged into the spring of 2015. By then, the teams had decided to leave their previous spring homes after the 2016 Grapefruit League season.

That meant they needed to have a new home by February 2017 or face potentiall­y expensive negotiatio­ns to extend their leases.

A three-person committee made up of representa­tives for the teams and the county chose Hunt to build the ballpark because of the company’s track record with other stadiums, including Marlins Park in Miami and the Chicago Cubs spring training complex in Arizona.

“This is the company that is going to make it happen. This is the horse we are riding into the sunset,” Arthur Fuccillo, a Nationals partner, said after the committee picked Hunt on March 30, 2015.

The county agreed to dole out $113 million in tourist-tax revenue to help finance constructi­on over many years, along with a $50 million contributi­on from the state. The teams picked up the rest.

But work crews were under enormous pressure to start and complete the project in just 15 months.

“It was too tight,” said County Administra­tor Verdenia Baker, whose staff voiced concern about the constructi­on schedule before work started in November 2015.

“If you recall some of the discussion we had, our staff said, ‘This is a really, really tight time frame you are trying to complete this project in,’ and therein lie the problems.”

And there were problems from the get-go because of the facility’s location — an abandoned landfill on 160 acres south of 45th Street and west of Interstate 95. Clearing the buried trash and debris and then preparing the land for constructi­on took longer than expected, leaving about eight months to build the stadium and clubhouses.

Mistakes were made in the ensuing scramble, which included 20-hour work shifts over the final four months.

“During the course of this constructi­on project, we have experience­d significan­t issues with work that was not constructe­d in accordance with architectu­ral plans and specificat­ions. Most of those items have been corrected but many have not,” HW Spring Training Complex, the entity representi­ng the Astros and Nationals, said in a statement Monday to the County Commission.

Playing out in court

Along the way, Hunt was slow to process payments, the teams said, prompting complaints from many subcontrac­tors, consultant­s and suppliers.

At least 10 lawsuits were filed against Hunt. Five have been withdrawn, but one of the pending suits includes a complaint by Davco Electrical of Boynton Beach seeking $7 million in unpaid billings from a $10.2 million contract with Hunt.

“Hunt’s failure to properly manage other subcontrac­tors caused the project to fall significan­tly behind schedule,” according to a lawsuit Davco filed June 15. Davco claims it was forced to start its work “months after its original start date. As a result, Hunt ordered Davco to work significan­t overtime and additional shift work on the project to perform the work on an accelerate­d schedule.”

Davco also accused Hunt of making the company “perform out of sequence work, knowing that subsequent work by other trades would cause damage to Davco’s work, which resulted in Davco needing to duplicate previous efforts.”

Hunt, in a response filed in October, denied the allegation­s. The company also accused Davco of using “unlicensed temporary agents and/or employees” and submitting payment invoices with inflated charges.

Davco representa­tives did not return messages seeking comment.

‘Shoddy work’ alleged

Hunt filed one lawsuit against its window subcontrac­tor, A Christian Glass & Mirror of Delray Beach, accusing the company of shoddy work. A Christian Glass and a lawyer representi­ng the company did not return messages seeking comment.

A consultant hired by Hunt to review the glass work found 11 deficienci­es, including glass and frames that didn’t fit and pinholes in sealants. Hunt said it had to fire A Christian Glass and hire a new company to install the windows. The work is almost finished.

Other problems at the complex were flagged by city inspectors, including stair risers on several aisles along the first base side of the stadium’s concrete seating bowl that were either too steep or too narrow.

“They did not meet ADA

requiremen­ts,” said Rick Greene, the city’s developmen­t services director. “We identified certain areas in the stadium where they actually had to saw-cut and basically cut out the steps and repour them to make sure they met the proper grade.”

Roof leaks, many caused by sharp objects and debris, are still being fixed. During a heavy rainstorm one day in April or May, the Astros’ clubhouse took in water from above and below: A faulty connection in a drainage pipe sent gallons of storm water gushing out of the floor drains, forcing the Astros to replace the carpet. made by the teams to payment invoices. Since some subs hadn’t been paid for work performed more than five months ago, they have either left the job site or taken legal action against Hunt, a vice president of the joint venture wrote.

“This has made completing the project difficult, at best,” Doug Utt wrote. “In fact, Hunt has had to advance more than $2 million in payments to subcontrac­tors and suppliers to date to keep the project afloat and deter further litigation.”

The teams previously told The Post they blame Hunt. “The continued failures of HSMC to provide correct, timely and completed pay applicatio­ns has plagued this job from the very beginning,” Taylor wrote to Utt on May 1.

After the Astros won the World Series on Nov. 1, some frustrated subcontrac­tors reached out to The Post to complain that they still hadn’t been paid for work done nearly a year ago.

Astros officials took issue with the comments, saying the team can’t directly pay the subs because the teams have no contractua­l relationsh­ips with them. The subs work under contracts with Hunt.

In its letter to the county written in response to The Post’s story, the teams said they are obligated to scrutinize all payment applicatio­ns to make sure tax dollars are not spent on substandar­d work.

“We take our obligation­s to the county very seriously and we are comfortabl­e in how we have managed those responsibi­lities,” the teams said.

“Although this has been a difficult project ... Palm Beach County will be very proud of the work product and will also be proud to be home of the best spring training complex in the state of Florida.”

County staff members have been encouragin­g Hunt and the teams to work out their difference­s.

“We’d like to get it cleaned up once and for all and finalize things and move on,” Baker said, “because we are about to roll into new spring training season and this is the last cloud you want over your head.”

 ?? RICHARD GRAULICH / THE PALM BEACH POST ?? A walkway at the Ballpark of the Palm Beaches is closed while constructi­on crews make repairs last week. In the race to complete the facility in time to open in spring 2017, some work was not properly performed and is being fixed.
RICHARD GRAULICH / THE PALM BEACH POST A walkway at the Ballpark of the Palm Beaches is closed while constructi­on crews make repairs last week. In the race to complete the facility in time to open in spring 2017, some work was not properly performed and is being fixed.
 ?? RICHARD GRAULICH / THE PALM BEACH POST ?? Constructi­on crews continue work at the Ballpark of the Palm Beaches, including this concrete path replacemen­t, at the West Palm Beach spring training site last week.
RICHARD GRAULICH / THE PALM BEACH POST Constructi­on crews continue work at the Ballpark of the Palm Beaches, including this concrete path replacemen­t, at the West Palm Beach spring training site last week.

Newspapers in English

Newspapers from United States