Demolition of historic barn delayed

- By Eric Devlin edevlin@21st-centurymed­ia.com @Eric_Devlin on Twitter

SCHUYLKILL TWP. >> A historic barn in Schuylkill Township will avoid the wrecking ball for at least another year, thanks to a new agreement reached between the township and the Phoenixvil­le Area School Board.

The school board unanimousl­y approved a 15-month continuanc­e with Schuylkill Township for continued use of a barn on the site of the former Meadow Brook Golf Club. The continuanc­e allows the school board to work through the details of the barn’s future as it decides whether’s its worth it to save the structure. The Schuylkill Township Board

of Supervisor­s already approved the continuanc­e at its last meeting Wednesday but needed the school board’s approval too.

“Schuylkill Township wanted us to vote on this as quickly as possible,” said board President Dan Cushing. “So that’s what’s bringing this as new business as opposed to waiting until next week. I don’t think it changes the outcome but they did request it specifical­ly and I think it’s appropriat­e for us to honor that municipali­ty’s request.”

The barn dates back to the Civil War and is part of a larger farmstead on the Meadow Brook property built before the Revolution­ary War. The district purchased the property two years ago in order to further its plans to build the incoming Phoenixvil­le Early Learning Center and Manavon Elementary School, currently estimated to cost $71 million. Last month, members of the Schuylkill Township Historical Commission lobbied for its preservati­on after district representa­tives asked for a permit to demolish the building. The school board then agreed to hold off on that request and installed a fence around the structure.

At Thursday’s school board meeting, board member Kevin Pattinson announced the district has obtained insurance for the barn and must now decide what steps will be taken regarding the building’s future. To do this, the building and grounds committee will assemble a taskforce composed of school board and community members, to serve in an advisory role.

The school board will need to make several decisions about the barn starting with how to renovate the space. If it were to renovate the structure to serve as office space, estimates show such work would cost approximat­ely $1.2 million, Pattinson said. If it decided to turn it into a classroom, it would cost approximat­ely $1.8 million.

The Schuylkill Township Historical Commission hired its own contractor to estimate the cost of simply renovating the building so it’s structural­ly safe, and found the price tag would be approximat­ely $600,000.

That figure does not include the cost of remediatin­g contaminat­ed soil left over from old engine oil, Pattinson said.

If the board decides to move forward with restoring the historic building, it must first determine what to do with that soil, he said.

“There’s no way they can move any equipment in there to do the digging,” he said. “I believe it has to be done by hand. There’s simply not enough space to do any excavating.”

If the board were to choose to simply demolish the barn, it would only have to cover over the soil. By demolishin­g the barn, the district would spend approximat­ely $52,000, according to Stan Johnson, executive director of operations. However, by selling off the building’s timber and leaving the stone on site, it could save approximat­ely $10,000.

The board would also have to decide what it would do with the barn after renovation. One suggestion included leasing it to a nonprofit organizati­on. The district would have to determine the legality of such amove first, Pattinson said.

Another suggestion would be for the board to consider the farmhouse and the barn linked and purchase them both.

“What is the district willing to spend for both of these buildings?” Pattinson said. “Wewill have to discuss how far are we willing to go as a board in saving these two historic buildings?”

Despite the fact that the building hasn’t deteriorat­ed since the property was purchased, the district stated last month that the building was structural­ly unsafe, uninsurabl­e and therefore a liability should anyone get hurt there. The school board later agreed to take on the building’s liability and crews installed an eight foot metal fence around the barn to prevent anyone from going inside.

“We will have to discuss how far are we willing to go as a board in saving these two historic buildings?”

— Kevin Pattinson, Phoenixvil­le Area School Board