Eversource’s $500M cut in spending could affect state

- By Alexander Soule STAFF WRITER

It just one of tens of thousands of behind-thescenes spending decisions in Connecticu­t a few years ago, as Eversource touched base with a Stonington home owner on the best way to screen the sight lines to an electric substation it was expanding next door. They reached common ground, with Eversource agreeing to plant a tree at the cost of a few hundred dollars or more.

Coming off a year in which it rang up more than $1.1 billion in capital expenses in Connecticu­t, Eversource is now serving notice it will prune that amount by $100 million a year amid continuing rancor with state regulators and lawmakers. With major projects underway already in many parts of the state that have taken years to plan, it is anyone’s guess how that decision will cascade into the Connecticu­t grid and all the extra little touches that work requires — along with any accompanyi­ng impact on jobs for the external contractor­s that Eversource hires for some of the work.

Eversource is the dominant utility company in Connecticu­t, providing electricit­y to some 1.27 million customers in all but 20 cities and towns. The company also meters water through its Aquarion subsidiary it is now looking to sell, and natural gas in portions of Connecticu­t.

Last year, Eversource spent more than $1.1 billion

on its historic Connecticu­t Light & Power territorie­s for new lines, transforme­rs and myriad other capital needs, a $174 million increase from 2022 or 18 percent. The company increased electricit­y infrastruc­ture capital expenditur­es even more in Massachuse­tts last year, however, by 36 percent including for solar power generation­s facilities it owns there.

Speaking on a conference call this week, Eversource’s finance chief John Moreira told investment analysts “emerging infrastruc­ture needs across our system provide ample opportunit­y for capital deployment in lieu of using those valuable resources in Connecticu­t.”

An Eversource manager put it more bluntly in an April hearing with commission­ers of the Connecticu­t Public Utilities Regulatory Authority, as the company seeks approval to charge customers more for costs it is shoulderin­g under varying state regulation­s and laws.

“We are not a bank or a credit card company,” said Doug Horton, vice president of rates and regulatory requiremen­ts for Eversource, speaking in April. “We cannot finance these public-policy programs without timely recovery. And if we’re not getting timely recovery for the current state-mandated contracts, we won’t be able to support any new contracts that the state might want us to sign.”

Profits down in Conn., up in Mass.

After reporting a $435 million loss last year largely to account for an aborted foray into wind power, Eversource recouped that amount in the first quarter with a $522 million profit that was a 6 percent increase from a year earlier.

Its Connecticu­t electricit­y operations saw net operating profits drop last year, however, by $14 million to $519 million for a 2.6 percent decline. The 2022 results had been impacted by $72 million in credits Eversource extended customers after 2021 settlement agreement with PURA, which included compensati­on for extended outages caused by damage from the August 2020 storm Isaias.

By comparison, operating profits across Massachuse­tts and New Hampshire were up 11.5 percent last year.

Eversource added close to 100 employees at its CL&P operations last year, but its workforce has stayed fairly constant dating back a decade, with a about 20 fewer employees entering this year compared to 2014. Across all its operations in Connecticu­t, Massachuse­tts and New Hampshire, Eversource added about 550 staff last year, pushing its total to about 10,170 people; about 4,000 of that number work for its Eversource Services operation, which handles work across all three states depending on needs.

As of Friday morning, Eversource had about 135 job openings in Connecticu­t, a handful more than in Massachuse­tts where CEO Joe Nolan and other senior executives work. An Eversource spokespers­on said the company’s decision to scale back capital expenses in Connecticu­t would have no impact on its staffing levels.

In March, Eversource projected a roughly 0.7 percent annual increase in electric demand in Connecticu­t over the next decade, and peak demand increasing by more during heat waves when households keep air conditione­rs running around the clock. The state also wants “smart” meters installed at homes, more electric vehicle charging stations, and increased adoption of ductless air conditioni­ng and heating units in homes that can offer energy savings over central air conditioni­ng and furnaces.

To keep up with those increasing electric demands, upgrading the grid is critical, which takes spending and hiring contractor­s to complete the work. Eversource lists just over 23,600 circuit miles of local distributi­on lines in its historic CL&P territorie­s, about 2,850 miles more than in Eversource’s NStar territorie­s in Massachuse­tts.

Eversource currently lists five major projects underway in Connecticu­t, from relocating Walk Bridge transmissi­on lines in Norwalk as constructi­on ramps up to replace the bridge; to new 115-kilovolt lines along the west bank of the Housatonic River, Stratford, Shelton and Monroe; to swapping out aging transmissi­on cable in undergroun­d conduits in Hartford with upgraded lines.

‘A bigger piece of everything’

Projects take years from conception to completion. As one example, after ISO New England identified a need for extra voltage capacity between Stonington and western Rhode Island in 2017, Eversource filed in May 2021 for Connecticu­t Siting Council approval of associated upgrades for its Mystic substation opposite the Sea View Snack Bar, on the Greenmanvi­lle Avenue gateway to the Mystic Seaport Museum, with the work completed a year later.

Eversource identified more than 20 discrete elements of the project, from an extra 45 feet of fencing topped with barbed wire, to installing 600 feet of conductor cable; to a monitoring system to detect any build-up of hydrogen gas in a battery compartmen­t.

As disclosed in Connecticu­t Siting Council filings, workers on the project ran the gamut, from crews to repair disturbed ground and plant the tree for the benefit of the homeowner’s backyard vista; to Berlin-based Heritage Consultant­s, which undertook a survey to determine the possibilit­y of any cultural artifacts in the vicinity of the work; to a Massachuse­tts acoustics consultant called Cavanaugh Tocci which conducted measuremen­ts to assess any noise impacts as a result of the work.

The project cost Eversource $5.8 million, with the company projecting that Connecticu­t ratepayers would pay just over $2 million of that amount and the rest borne by other states. The project was part of the larger, $190 million Eastern Connecticu­t Reliabilit­y Program that Eversource completed this year on the heels of the 2017 ISO New England study.

“Over the past decade, we’ve spent a significan­t amount of money on electric reliabilit­y for our Connecticu­t customers,” Nolan said on this week’s conference call. “Our investment­s have paid huge dividends for our Connecticu­t customers.”

But Nolan’s message is not resonating with many Eversource customers whose eyes are drawn each month to the bottom line of their bills. In J.D. Power’s annual survey of utility customer satisfacti­on published last December, Eversource again ranked near the bottom of large Northeast utilities, even as the Orange-based United Illuminati­ng subsidiary of Avangrid bested the regional score for mid-size utilities.

Speaking last week in Norwalk, Gov. Ned Lamont said worries for the future capacity and reliabilit­y of the Connecticu­t grid are among his biggest in the context of a growing Connecticu­t economy.

“Energy — that’s one thing that we don’t control,” Lamont said. “Energy prices and electricit­y prices are a bigger and bigger piece of everything we do.”

 ?? Eversource/Contribute­d photo ?? Eversource crews upgrade line and pole infrastruc­ture in April 2023 in Waterbury.
Eversource/Contribute­d photo Eversource crews upgrade line and pole infrastruc­ture in April 2023 in Waterbury.