The Reporter (Lansdale, PA)

Air conditioni­ng talk brings a little heat

District officials discuss adding AC to 3 middle schools

- By Dan Sokil dsokil@21st-centurymed­ia.com @Dansokil on Twitter

LANSDALE >> With a new school year now underway, and kids back in classrooms, North Penn officials are resuming a discussion that began pre-pandemic.

How should the district tackle the question of adding air conditioni­ng to the three middle schools that currently don’t have it?

“Back in 2016, there was an estimate provided by an architect for air conditioni­ng in the middle schools, and also Gwyn-Nor, Knapp, and Oak Park” elementary schools, said district director of Facilities and Operations Tom Schneider.

“Gwyn-Nor and Oak Park had air conditioni­ng installed, Knapp is currently under renovation­s, and then we had estimates for air conditioni­ng at Pennbrook, Pennfield, and Penndale,” he said.

In 2016, early estimates from the architect were that installing air conditioni­ng at all three schools would cost roughly $30 million, with Pennbrook estimated at $7.8 million, Pennfield estimated at $8.8 million, and

Penndale roughly $12.9 million, Schneider told the school board’s facilities and operations committee in late August.

“This air conditioni­ng cost was only for the main building, and not doing anything to the existing modular classroom structures that are on Pennfield and Pennbrook,” he said.

Pennbrook currently has 22 modular classrooms and Pennfield 14, according to Schneider, and the roughly $30 million estimate does not include any new constructi­on to add permanent classroom space.

“It would be an awful lot of expense to install air conditioni­ng in those buildings, and then possibly, in the future, if there is renovation soon, eliminate the modular classroom structure, and turn it into permanent constructi­on,” Schneider said.

“The air conditioni­ng plant would have to be completely redone, basically removed and replaced,” he said.

In 2019 the district began public discussion­s that could also impact the future of those middle schools: whether to change the district’s grade level structure, and move ninth grade from the three middle schools to North Penn High School, a change that could leave the middle schools with only seventh and eighth grades, or prompt sixth grade to move from elementary to middle schools.

“We knew we would need to do the rest (of the high school) before ninth grade actually moves there,” said Superinten­dent Curt Dietrich.

“And then, once ninth grade is located at the high school — if that comes to fruition — then make a determinat­ion if we want to stick with K-through-six, and then seven-and-eight, or have a K-through-five and six-through-eight at the middle schools,” he said.

One other factor that would need to be further studied, Dietrich added: Could changing the grade levels mean one of the schools is no longer needed?

“Depending on the grade structure, we might not need Penndale. And then, if we don’t need Penndale, it just didn’t make a lot of sense to dump a lot of money into something that would either be sold or demolished,” he said.

Schneider added that the $30 million cost estimates from 2016 would likely be higher now due to constructi­on material and labor shortages caused by COVID-19.

“We could possibly see a project cost reaching about $40 million in today’s dollars, with the way constructi­on costs are today. It’s just something to keep in mind,” he said.

Board member Jonathan Kassa said those talks were partially what led the board to push staff to develop a ten-year capital plan of needed facilities upgrades, and approved upgrades to add air conditioni­ng at Gwyn-Nor and Oak Park first, then the full Knapp renovation.

“It’s clear why we didn’t do Knapp, because of this full renovation. That same type of logic and approach then applies to the middle schools,” he said.

“That’s part of the issue that we brought up to the community as a whole: Are we going to renovate North Penn High School? And if that need exists, well then the rest of the priorities have to come in place,” Kassa said.

Kassa then asked Schneider for specifics on an equipment failure at the high school at the end of the 2020-21 schoolyear, and Schneier said a chiller in the school’s K-pod that was installed in 1996 had failed, and was replaced at a cost of roughly $165,000.

“That was unplanned — although it was on the list. We knew we’d have to get to it,” Kassa said.

Board members have approved upgrades to the modulars at Pennbrook, and a study of the needs within the high school which could spell out where to add the possible ninth grade center, Kassa added, all steps needed before any more major projects begin.

“That’s why we need to have this discussion. None of us are happy with the lack of air conditioni­ng. There was no plan three years go. There’s a plan now,” he said.

Kassa then asked Dietrich if air conditioni­ng could be installed sooner at the middle schools than a major renovation.

“It would be extremely difficult to be able to do this, in a way that is most cost-effective, if we piecemeale­d it and try to introduce the air conditioni­ng now,” Dietrich said.

“It is extremely important that we go to the high school. In my opinion, the high school really has to be next — we are having some challenges with the pneumatics there, we had some challenges recently, it’s just an old, old system there,” he said.

Late August rainstorms caused roof drainage issues and penetratio­n of water into the building envelope, he added, and any high school project must follow the grade-level discussion first.

“Do we want to stick with seven-and-eight? Or do we want to move to sixto-eight? It has a lot of ramificati­ons, also, at the elementary level, in terms of program implicatio­ns there. We also have modulars at some of our elementary schools,” which could also be phased out if students are moved to other schools, he said.

Student liaison Eric Wang asked if the district had a cost estimate to replace the modular classrooms with new constructi­on. Schneider said no formal project has been bid or examined, but new constructi­on runs roughly $250 to $300 per square foot, and Dietrich said a typical classroom of about 850 square feet would produce a cost of $250,000 to $300,000 per classroom.

“I anticipate we’re going to replace them with permanent constructi­on, that’s been the direction this board has been steadfast on, but that’s rough math,” Dietrich said.

After the presentati­on and board discussion, two Republican candidates running for school board questioned the current board’s priorities.

“The ten-year facilities plan is great. I’d like to know where the stadium was on that plan, as far as the rating goes,” said candidate Jessie Bradica.

“Our tax dollars are in that capital reserve fund. This board had a $3 million budget surplus the first year that they were on the board. Then, in 2018-19, they raised the taxes above the Act 1 index to claim exceptions — which resulted, then, in another $3 million budget surplus. Which again went into the capital fund,” she said.

Board candidate Fred Froehlich added a comparison between the cost of the Crawford project and the early estimates for the middle schools.

“At minimum, Pennbrook should’ve been air conditione­d before we had a stadium. It could’ve been done prior to the stadium,” he said.

“I was in Penndale, and it was 85-plus degrees the other day, when my daughter made her first entrance into the building. Imagine masks, 80-plus degree weather, and going to school every day for seven hours, nobody on this board would do it. None of our kids should have to do it,” Froehlich said.

Kassa added that he looked forward to ongoing discussion­s, but asked that the candidates keep campaign rhetoric out of the discussion­s.

“We need to deal with the air conditioni­ng, but let’s not use that to exploit what the community has been going through, when this administra­tion, our staff, and my fellow board colleagues are working very hard to serve this community as best we can, under the conditions,” Kassa said.

North Penn’s school board next meets at 7 p.m. on Sept. 15 and the facilities and operations committee next meets at 7 p.m. on Sept. 27; for more informatio­n visit www.NPenn.org.

 ?? DAN SOKIL MEDIANEWS GROUP ?? North Penn school board members and staff listen to public comments during their Aug. 11 meeting at Penndale Middle School.
DAN SOKIL MEDIANEWS GROUP North Penn school board members and staff listen to public comments during their Aug. 11 meeting at Penndale Middle School.

Newspapers in English

Newspapers from United States