The Sentinel-Record

Multiple water system upgrades underway

- DAVID SHOWERS

More than $4 million was committed through the end of last year from the $20 million bond issue the city floated for capital improvemen­ts to the regional water system serving more than 35,000 meters inside and outside the corporate limits, according to a report from the city finance department.

The $4,114,324 does not include the $1,189,640 contract the Hot Springs Board of Directors will consider at its business meeting Tuesday night. It will pay for new switchgear and a motor-control center at the plant treating water collected by the intake at upper Lake Hamilton. The roughly

$500,000 outlay the board authorized in October for the purchase of 33 acres on Little Mazarn Road for the constructi­on of a new treatment plant has also yet to be added to the total.

The city has earmarked $5 million in bond proceeds for preliminar­y engineerin­g, design and right of way acquisitio­n for the roughly $100 million project to bring its 23 million-gallon average day allocation from Lake Ouachita online. The balance of the funds is dedicated to other improvemen­ts, not including work being done to the elevated storage tank on Hollywood Avenue.

The $746,950 contract the board awarded Classic Protective Coatings Inc. of Wisconsin in August was paid from the remaining balance of a 2015 debt issue. The cost includes painting the city logo on the exterior of the 1 million-gallon tank.

Matt Dunn of Crist Engineers Inc., the city’s water system consultant, told the board earlier this week the logo will be painted on the east and west sides of the tank, with the west side being discernibl­e from as far away as Oaklawn Racing and Gaming.

The interior is being recoated and outfitted with a mixing system designed to improve water quality on the south and east ends of the system’s 145-squaremile service area. Trihalomet­hane concentrat­ions

exceeding the Environmen­tal Protection Agency’s 80-partsper-billion limit have been detected in those areas, as their distance from treatment plants at the northwest and north ends of the system promotes the formation of the chemical compound.

A byproduct of the interactio­n between chlorine used in the treatment process and organic material in the water, THMs become more pronounced the longer treated water remains in the distributi­on system. The state Health Department has said EPA research linked an increased risk of liver and kidney cancer to long-term exposure to high THM concentrat­ions.

The Hollywood tank is the primary feeder for customers on the south and east ends of the system. Adding a mixing capability will direct older water at the top of the tank to the bottom, where it can be distribute­d before the newer water. System operators currently have no way to circulate the contents of the tank, leaving older water in storage longer and increasing water age for customers on the system’s outer edges.

Cornerston­e tower

The $20 million bond issue includes funds for the 190-foottall storage tower being built behind Cornerston­e Market Place. The city committed $858,813 from the bond issue toward the

$4,647,000 contract the board awarded Chicago Bridge & Iron LLC of Georgia in June. The balance was paid from the 2015 bond issue.

It will be the first elevated tank added to the distributi­on system since the Hollywood tank came online in 1964, the city has said, holding 3 million gallons that can tie into the 20inch transmissi­on line that runs along the King Expressway.

Constructi­on is 30 percent complete and is expected to conclude next winter.

“We’re waiting for the pedestal crew to come in next,” Dunn said earlier this week, explaining that foundation work that’s been completed required the pouring of 1,000 feet of concrete supported by more than

600,000 pounds of steel rebar. “Three million gallons weights a lot. You have to have a big load undergroun­d to hold that water in the air.”

Northwoods dams

Core samples for geotechnic­al analysis of dams impounding lakes Sanderson and Dillon at the Northwoods Urban Forest Park have been completed.

The analysis is part of the $1,209,350 contract the board awarded Crist in July for engineerin­g work on improvemen­ts expected to cost almost $10 million.

The park’s three small lakes, including Bethel, were decommissi­oned as a municipal water source decades ago. Hewed from a nearby mountain, the masonry that forms Dillon Dam is more than a century old. Vegetation that has encroached over that time has loosened the mortar that binds the bricks together, as evidenced by the tree that has sprouted from the middle of the structure. Encroachin­g vegetation has also affected the structural integrity of Bethel Dam, engineers have said.

Switchgear

The $1,189,640 contract the board will consider Tuesday night for a Kohler switchgear and master control center at the water plant on upper Lake Hamilton will also be paid from the

$20 million bond issue. It’s part of the almost $4 million project to replace the system that controls high-service pumps that push treated water through two large diameter distributi­on lines leading from the plant.

The equipment will be located on the 4.5 acres adjacent to the plant’s Cozy Acres Road location the city acquired for

$113,450 last year.

The board awarded Crist a

$298,250 contract to design the control system and oversee its installati­on.

 ?? The Sentinel-Record/Richard Rasmussen ?? TANK MAKEOVER: Arms extending from the Hollywood Avenue water tank support a curtain that’s raised when crews are painting the city logo on the 1 million-gallon structure. The city said the final coat will be applied soon.
The Sentinel-Record/Richard Rasmussen TANK MAKEOVER: Arms extending from the Hollywood Avenue water tank support a curtain that’s raised when crews are painting the city logo on the 1 million-gallon structure. The city said the final coat will be applied soon.

Newspapers in English

Newspapers from United States