Streetscape construction continues Where will the work occur?
Did you know that some of the water and sewer lines being replaced are over 100 years old? For decades now, our downtown buildings have been plagued with plumbing problems due to the aging pipes…not after this!
The construction crew has begun the work of replacing water lines between Church Street and Henry Street. (Check out the picture!)
This work will continue throughout the next four-five weeks; then, the crews will shift to the south end of the project between Mill and Church streets.
Pedestrian access to businesses will be maintained at all times. Please note that, while we make our best effort to forecast construction impacts, this is inherently messy work that is subject to change based on conditions in “the field.”
Replacement of water lines and other related construction activities will occur on State Street between Church and Henry streets.
What are the construction days/hours?
This week’s construction days/hours are scheduled for Monday-friday, 6 a.m. — 6 p.m.
Will there be night work?
No. There is no night work scheduled this week.
Will there be dust and noise?
Yes. There will be ongoing dust and noise due to the water line trenching and truck and equipment activity in the construction area.
Will there be any disruptions to parking access or streets?
Yes. Through traffic will be maintained on State Street, but will be
reduced to two lanes with limitations to parking on South State Street between Church and Henry streets.
Standley and Smith Streets will be temporarily closed between Friday, July 10-July 17.
More information can be found online on the city’s website at ukiahstreetscape.com, or follow our Facebook page for updates and photos at facebook.com/ukiahstreetscape/.