Times Chronicle & Public Spirit

Montgomery County Justice Center project adds $2M in contracts

Agreement amendments awarded in 2-1 roll call vote

- By Rachel Ravina rravina@thereporte­ronline.com

NORRISTOWN >> The ongoing constructi­on of the Montgomery County Justice Center was awarded another $2.04 million in contracts for constructi­on management and architectu­ral and engineerin­g services.

An agreement previously authorized with Skidmore, Owings & Merrill LLP of Washington, D.C., to design the justice center and expand Hancock Square called for another $1,333,473 for “staffing and systems resources for structural design modeling and coordinati­on, additional staffing resulting from the delayed NPDES permitting process, redesign of DRO office space at owner direction, and additional constructi­on administra­tion staffing to account for constructi­on contractor performanc­e issues,” the contract states.

The contract has been revised twice and the total figure is now listed at $27,444,369.

Additional­ly, a constructi­on management contract with Skanska USA, of Parsippany, N.J., required another $709,568 for “staffing for guidance, management, and data collection for the project’s community participat­ion program, installati­on and management of the project site monitoring and progress camera system, additional utility discovery and documentat­ion, additional LEED coordinati­on based on design and cost and constructa­bility review for DRO space design revisions.”

The contract was initially authorized at $5.18 million and has since been revised four times. The updated figure now stands at $14,513,783.

The two previously authorized contracts were amended during last week’s Montgomery County Board of Commission­ers meeting. The package passed in a 2-1 roll call vote with Montgomery County Commission­er Joe Gale dissenting.

“I’d like to point out that the original contract with Skanska started at $5 million,” Gale said. “It’s now gone to $14.5 million and the original contract with Skidmore, Owings & Merrill started at $16 million. That’s now increased to $27.5 million, and in my opinion, this level of spending is entirely too high, and I’m opposed to these expenses.”

Montgomery County Commission­ers Chairwoman Val Arkoosh sought counsel from Deputy Chief Operating Officer Barbara O’Malley regarding budgetary concerns associated

with the project.

“Ms. O’Malley, just to clarify this … is within the original budget of the project and these changes will not impact the project, which is still on budget?” Arkoosh said.

“Yes, that is correct,” O’Malley replied.

Along with Gale, several area residents expressed their frustratio­ns with the project’s expenses and stressed the need for a forum during the meeting’s public comment portion.

The $415 million Montgomery

County Justice Center project broke ground in June 2021. The project is expected to construct a 508,150-square-foot facility. It’s unclear when the project will be finished.

The next Montgomery County Board of Commission­ers meeting is scheduled for 10 a.m. on Nov. 17 on the eighth floor of One Montgomery Plaza, located at 425 Swede St. in Norristown. Those interested in attending the meeting can do so virtually. Visit montcopa. org for more informatio­n.

 ?? ?? Pardon our appearance — The newly updated One Montgomery County serves as a pleasant background to the constructi­on site for the Justice Center.
Pardon our appearance — The newly updated One Montgomery County serves as a pleasant background to the constructi­on site for the Justice Center.

Newspapers in English

Newspapers from United States