FAST DELIVERY
Monte Carlo Yachts can build the MCY 70 Skylounge with four months of lead time. The hull, interior accommodations and superstructure can be built in parallel on three separate production lines, with the interior dropped into the hull as soon as it’s ready, then capped by the superstructure. Solid fiberglass is used below the waterline, and carbon fiber and Kevlar are also used in the build to reduce weight while maintaining strength.