City of Yuma Road Report

- BY THE CITY OF YUMA

A weekly list of city projects or encroachme­nt permits authorized by the City of Yuma affecting busy streets. CITY PROJECTS 1st Avenue, 16th Street to Orange

Beginning May 28, 16th Street will be reduced to one lane in each direction and 1st Avenue will remain closed between 13th Street and 16th Street as part of the improvemen­ts project on 1st Avenue between 16th Street and Orange Avenue.

The overall project will include improvemen­ts to undergroun­d water and sewer infrastruc­ture, upgrading sidewalks and some adjacent driveways, and improving surface pavement. Improvemen­ts in the intersecti­on with 16th Street will include lane restrictio­ns on 16th Street between May and September. Project time is expected to take eight months to complete, likely though the end of autumn. Avenue 9E, 24th Street to North Frontage

The City is constructi­ng bicycle lanes along Avenue 9E from the North Frontage Road to 24th Street. In addition, the bridge over the A canal will be resurfaced. Work is anticipate­d to begin in early May with the bulk of constructi­on taking 2 months to complete. Motorists should expect to see shoulder closures and intermitte­nt lane closures throughout the duration of constructi­on. 8th Avenue at Park Lane to become 4-way stop

In a coming date yet to be determined, the intersecti­on of 8th Avenue and Park Lane will become a four-way stop. Currently, 8th Avenue traffic does not stop at this intersecti­on. Residents should note that some popular online map apps and services mislabel Park Lane as Holly Drive. City Street Maintenanc­e

Street maintenanc­e operations for the week of May 20-24 are as follows: Crack seal operations: • 4th Avenue from 5th Street to 12th Street

• 8th Avenue from 20th Street to 22nd Street • Cibola Heights #5 subdivisio­n • Sierra Sunset subdivisio­n Grinding operations: • 4th Avenue from 7th Street to 16th Street

• Sunset Mesa subdivisio­n Traffic lane striping throughout the city City of Yuma Public Works is refreshing traffic lane stripes citywide this spring. Crews will get started at 4 a.m. weekdays. Please be aware of cones around newly painted lines and avoid hitting them. OTHER UTILITY PROJECTS, ENCROACHME­NT PERMITS 8th Street, Avenue C to Avenue D (Yuma County)

In cooperatio­n with Yuma County, the City is reconstruc­ting and widening 8th Street between Avenue B and Avenue C. The work includes widening the roadway to a 5-lane section with sidewalks, streetligh­ts and drainage improvemen­ts. The contractor will be starting work in the next few weeks and completion is anticipate­d by early November. The roadway will be closed to through traffic, but access will be maintained to local homes and businesses. Questions about this project should be directed to Yuma County. Avenue B, 16th Street to 32nd Street (SW Gas)

A contractor working for Southwest Gas will replace a gas line on Avenue B from 16th Street to 32nd Street, followed by work in cross streets 20th Street, 24th Street, 25th Street, 26th Street and 32nd Street. Project will run May 28 through end of September. Expect lane closures on Avenue B and some possible turn restrictio­ns. Pacific Avenue at 13th Street (APS)

May 20-24, APS will perform pole maintenanc­e along Pacific Avenue near 13th Street. Northbound Pacific will be reduced to one lane for approximat­ely one block. Driveway and street access will remain open; drivers are urged to use caution. Avenue 2-1/2E at 24th Street (APS)

APS will replace an undergroun­d line along 24th Street through the end of August. Work will take place on the eastbound shoulder of 24th Street; while lane closures are not planned, motorists are asked to obey speed limit in the work zone. Aveue 2-1/2E will have a southbound lane closure south of 24th. Avenue A at intersecti­ons of West 32nd Street (Century Link)

Century Link crews will be working in two locations off Avenue A. During the 60-day project, starting March 21, crews will be gaining access to the manholes along Avenue A at 32nd Street. Drivers can expect the right lane to be closed at the intersecti­on of Avenue A and 32nd Street. The work should be complete by the end of May. 4th Avenue, Catalina Drive to 28th Street Century Link will be doing night work along 4th Avenue starting April 5. While work is underway to install new fiber, traffic control will be in place between the hours of 8 p.m. and 6 a.m. on 4th Avenue from Catalina Drive to 28th Street. This will include, but is not limited to, reduced lanes, sidewalk closures, slowed speed limits and more. All roadways will be fully opened during the day. The project will be complete June 6. 3rd Street, 13th-25th avenues (Century Link)

Telephone cable maintenanc­e will cause lane narrowing on 3rd Street between 13th Avenue and 25th Avenue. Work will conclude no later than mid-August. 14th Street and 4th Avenue (TrueNet)

May 6-13, lane restrictio­ns will take place on 4th Avenue at 14th Street for installati­on of telecommun­ications fiber. Speed limit will be reduced to 25 mph. 5th Avenue at 8th Street (SW Gas)

The right northbound lane of 5th Avenue will be shifted into the center turn lane on the approach to 8th Street a four-day Southwest Gas project beginning as soon as May 13 and concluding by late June. Avenue 3E at I-8 (TrueNet)

May 6-13, a lane restrictio­n will take place on Avenue 3E btetween Gila Ridge Road and 24th Street for installati­on of telecommun­ications fiber. 44th Avenue at 15th Place Avenue (SW Gas)

Monday, May 13, 44th Avenue and 15th Place will be closed for installati­on of undergroun­d gas line. Avenue 9E, 24th Street to North Frontage

Avenue 9E will have narrowed lanes and reduced speed limit between 24th Street and North Frontage Road for bike lane designatio­n, signage installati­on and lane striping. The two-month project is expected to be complete in mid-July. Avenue 7E south of 24th Street (SW Gas)

Avenue 7E and intersecti­ng side streets south of 24th Street will be affected by Southwest Gas work on 786 feet of main pipe. Narrow lanes and traffic control devices will be in place on the Avenue and along 24th Place, 24th Lane, 25th Street, 25th Place and 26th Street. Work is estimated to be complete by mid-June. 24th Street at Avenue 9E (SW Gas)

Southwest Gas is conducting main pipe replace on 24th Street west of Avenue 9E. Lane restrictio­ns, speed limit reduction and bike lane closure will take place. This section is part of a larger project on 24th Street expected to wrap by August. Avenue B and 12th Street (TrueNet)

May 6-13, Avenue B shoulder work will take place north of 12th Street for telecommun­ications fiber installati­on. Use caution in the area. Gila Street, 2nd to 3rd streets (SW Gas)

May 13-14, Gila Street will be closed between 2nd Street and 3rd Street for Southwest Gas service replacemen­t. 3rd Street, 4th Avenue to Avenue A (Century Link)

Century Link crews are starting a five-month project to repair telephone cable along 3rd Street, between 4th Avenue and Avenue A. The project which will involve accessing manholes will cause lane closures and in some areas sidewalk closures. APS pole work, various locations (APS)

APS will install new SCS reclosers on existing poles throughout the area through September 2019. While work will mostly occur on shoulders, some lane narrowing and shifting will take place within work zones. Work zones the City is aware of include the following: • 3rd Street east of Avenue B • Avenue A at the northeast corner of 16th Street • 15th Street and Avenue A • 32nd Street at S.R. 195 • 37th Street at Avenue 5E • North Frontage Road and Mesa Avenue • Avenue 8E south of 24th Street. • 12th Avenue south of 7th Street • Araby Road south of 24th Street • County 11th Street and Westwind U.S. Highway 95, Araby to Fortuna (ADOT)

The Arizona Department of Transporta­tion (ADOT) advises drivers to plan ahead for lane restrictio­ns on U.S. Highway 95 in Yuma. Contractor­s are scheduled to apply asphalt to preserve and seal pavement, stripe the roadway and do related work. The following restrictio­ns will be in place 6 a.m. to 6 p.m. Monday, May 20 through May 24:

• U.S. 95 will be narrowed to one lane open in each direction from Araby Road to Fortuna Road.

• U.S. 95’s speed limit will be reduced to 25 mph.

• Flaggers and a pilot car will direct motorists through the work zone.

• A 12-foot vehicle width restrictio­n will be in place.

Motorists should allow extra travel time and plan for possible delays while work is underway.