Yuma Sun

Yuma County Road Report

- BY YUMA COUNTY

FarWest Storm Drain Improvemen­t Project

What’s New... Yuma County is installing a new storm drain system to alleviate flooding at several locations in the Foothills. The contractor currently allocated three undergroun­d crews and one grading crew in order to work at multiple locations:

• Farwest Avenue, South of 34th St.: 7/22/19 thru 7/26/19: Contractor to complete installati­on of valley gutters across roadway.

• Cassidy Avenue, South of 37th St.: 7/22/19 thru 7/26/19: Contractor to complete last catch basins on Cassidy &37th Pl. Once complete contractor to continue grading roadway for new pavement. Detour will be set thru 37th Street.

• Mona Avenue, North of 37th St.: 7/22/19 thru 7/26/19: Contractor to complete manhole and remaining catch basin along Mona Avenue. Grading roadway for new pavement will commence right after. PAVEMENT REPLACEMEN­T WILL INCLUDE FULL ROADWAY WIDTH. Detour will be set thru 37th St.

• Sandra Avenue, South of 37th St.: 722/19 thru 8/02/19: Contractor to continue installati­on of storm drain. Work expected to be completed by 8/02. Once storm drain is completed contractor with grading roadway for pavement. Detour will be set thru 37th Street.

• 38th St & Cassidy Avenue: 7/22/19 thru 7/26/19: Contractor will install new and catch basin at southeast corner of intersecti­on. Road will be closed to thru traffic, detour will be set thru 37th St.

Road Closures: 38th Street will be closed at Cassidy Avenue. Motorists can expect delays as several crews are conducting work, drivers are urged to pay close attention to work zone signs. Traffic control will be in place to detour traffic around road closures. Detour route will be set thru 37th Street and Hunter Avenue.

8th Street Road Improvemen­t Project, Avenue D to Avenue C

What’s New... As part of the reconstruc­tion of 8th Street, Yuma County will be conducting the following work:

• Full reconstruc­tion of an urban road section (approx.4,600 lineal feet) consisting of five lanes, two lanes in each direction and a central turning lane; mill and overlay intersecti­on of Avenue C & 8th Street.; installati­on of new storm drain pipe, manholes, and catch basins; installati­on of new pavement section, curb & gutter, sidewalk, exposed aggregate concrete, driveways, sidewalk ramps, pavement markings and signage; constructi­on of two stormwater detention basins, including pump station and storm sewer force mains, and outlet structures; installati­on of new street lighting and miscellane­ous items.

Schedule: Contractor mobilized May 20,2019. Work Expected to be completed by January 2019.

7/22/19 thru 7/26/19: For the first phase of work contractor is expected to conduct work on North side of roadway, including roadway excavation and new storm drain system. Storm drain installati­on commenced on 7/16 and is expected to continue until October 2019.

Road Closures: Vehicular traffic will remain on paved roadway, no road closures are expected during the initial phases of work.

Utility Work on County R/W.

• Co. 11th St, Between Avenue D & Somerton Avenue: 7/22/19 thru 7/23/19: APS will be closing Co. 11th St to install new service vaults and run conduits to new facility. As part of the work a portion of the roadway in this area will be removed and replaced. Detour will be thru Somerton Avenue & Co. 10th St and Avenue D thru Co. 14th St. Paving expected to be completed by 7/23/19.

YUMA WORK SCHEDULED (7/22/19-7/25/19)

GRAVEL ROAD MAINTENANC­E: • Route 1: South of Hwy 95 & West of Ave B

• Route 2: South of Co 14th St & East of Ave B WORK ZONES: • 7/22/19: Asphalt overlay on Co 11th St from Somerton Ave to Avenue E

• 7/22/19: Asphalt overlay on Co 11th St from Avenue E to Avenue D

• 7/23/19: Asphalt overlay on Avenue E from Co 9th St to Co 8th St

YUMA WORK SCHEDULED (7/29/19-8/01/19)

GRAVEL ROAD MAINTENANC­E: • Route 1: South of Co 8th St & West of Avenue D

• Route 2: South of Co 14th St & East of Ave B WORK ZONES: • 7/31/19: Asphalt overlay on Avenue D from Co 10th St to Co 9th St

• 7/31/19: Asphalt overlay on Avenue D from Co 9th St to Co 8th St

• 8/01/19: Asphalt overlay on Avenue 3E from Co 18 1/2 St to Co 19th St

MOHAWK VALLEY WORK SCHEDULED (7/22/19-7/25/19)

GRAVEL ROAD MAINTENANC­E: • Route 3: North of Hwy 80 & East of Ave 16E to Ave 22E

• Route 4: North of Hwy 80 & East of Ave 40E to Ave 45E

MOHAWK VALLEY WORK SCHEDULED (7/29/19-8/01/19)

GRAVEL ROAD MAINTENANC­E: • Route 3: North of Hwy 80 & East of Ave 22E to Ave 40E

• Route 4: North of Hwy 80 & East of Ave 45E to Ave 57E

SIGNAL MAINTENANC­E WORK SCHEDULED (7/22/19-7/25/19)

PREVENTIVE MAINTENANC­E: • Payson Dr & S. Frontage Rd • 28th St & Fortuna Rd • Fortuna Rd & 35th Pl • Fortuna Rd & 40th St • Foothills Blvd & 38th St • Fry’s entrance & S. Frontage Rd

SIGNAL MAINTENANC­E WORK SCHEDULED (7/29/19-8/01/19)

PREVENTIVE MAINTENANC­E: • Foothills Blvd & 48th St • Hwy 95 & Avenue 3E • Avenue 3E & 32nd St • Foothills Blvd & 40th St • Avenue A & Co 14th St

Newspapers in English

Newspapers from United States