Yuma Sun

County Road Report

- BY YUMA COUNTY

8th Street Road Improvemen­t Project, Avenue D to Avenue C

What’s New: As part of the reconstruc­tion of 8th Street, Yuma County will be conducting the following work:

Full reconstruc­tion of an urban road section (approx.4,600 lineal feet) consisting of five lanes, two lanes in each direction and a central turning lane; mill and overlay intersecti­on of Avenue C & 8th Street.; installati­on of new storm drain pipe, manholes, and catch basins; installati­on of new pavement section, curb & gutter, sidewalk, exposed aggregate concrete, driveways, sidewalk ramps, pavement markings and signage; constructi­on of two storm water detention basins, including pump station and storm sewer force mains, and outlet structures; installati­on of new street lighting and miscellane­ous items.

WEEKLY SCHEDULE: 06/08/2020 to 06/12/2020: Contractor will be working on completing punchlist items. Lane closure will be in effect as the work is taking place.

Road Closures: Road is open to vehicular traffic with two lanes of travel in each direction and a center turn lane. Lane closures expected to occur to complete remaining work.

Motorist are encouraged to follow all speed limits and detour signs.

MARTINEZ LAKE RD / CIP 1.1701 RED CLOUD MINE RD

What’s New: Contractor started constructi­on activities on March 30, 2020. Traffic delays possible.

General Descriptio­n: Work is located in the Martinez Lake Area. Work includes roadway improvemen­ts to Martinez Lake Rd from the Rural Metro Fire Station at Fisher’s Landing and extending southerly approximat­ely 6.25 miles past Yuma Proving Ground Jump School. Work along Red Cloud Mine Rd will extend from the intersecti­on of Martinez Lake Rd and extend northerly for about 2.1 miles. Road Improvemen­ts include grading, paving, drainage improvemen­ts (box culverts) and smoothing out the vertical alignment to improve safety and provide all weather access.

Constructi­on Start Date February 5, 2020

Estimated Completion Date April 2021

Project Contractor Intermount­ain West Constructi­on Company

Constructi­on Cost: $18,327,659.30

Master Schedule: Martinez Lake Rd/ Red Cloud Mine Rd: Weekday Lane Closure on Martinez Lake Road and Red Cloud Mine Rd with Flaggers and Pilot Car operations Started April 1, 2020 between 6 AM and 5 PM. Expect 15-20 minute Delay.

AVENUE B: COUNTY 16TH STREET TO COUNTY 18TH STREET INTERSECTI­ON IMPROVEMEN­TS PROJECT, CIP

NO. 1.0702

What’s New: As part of the reconstruc­tion of Avenue B, Yuma County will be widening five intersecti­ons along Avenue B to provide left and right run lanes from Avenue B, the intersecti­ons to be improved are: Co. 16th St, Co. 16-1/2 St, Co 17th St, Co. 17-1/2 St & Co. 18th St.

The work includes grading , mill and overlay pavement, installati­on of new pavement, and curb & gutter, pavement marking and signage, and minor traffic signal work at Co. 16th St.

Master Schedule: Cemex Constructi­on Materials South, LLC is expected to mobilize once utility relocation­s are completed. For the first phase of work contractor is expected to commence work at Co. 18th St and Avenue B and move north to work at each intersecti­on.

WEEKLY SCHEDULE: Century Link: 06/08/2020 to 06/12/2020: Century Link will be relocating their facilities onto the new APS poles on the east side of the road and abandon and remove all existing wood poles along west side of road. Century Links expects to complete all relocation­s by July/2020.

City of Somerton:

City of Somerton completed new waterline at the intersecti­on of Co. 16th St and Avenue B

Road Closures: Road is open to vehicular traffic with one lanes of travel in each direction.

Motorists are encouraged to follow all traffic control signs.

HIGHWAY 95 AND ENGLER AVENUE INTERSECTI­ON IMPROVEMEN­TS PROJECT, CIP NO. 1.9915(D)

What’s New: A new traffic signal will be installed at the intersecti­on of Engler Avenue and Highway 95, as part of the signal improvemen­ts designated left turn lanes will be provided at all approaches.

The work includes Installati­on of new pavement, turn lanes, raised median, curb & gutter, ADA ramps and driveways, installati­on of new traffic signal, installati­on of new street lighting, pavement marking and signage.

Master Schedule: Contractor expected to mobilize once utility relocation­s are completed. For the first phase of work contractor is expected to commence work on south side of intersecti­on.

WEEKLY SCHEDULE: APS & Century Link: 06/08/2020 to 06/12/2020: APS & Century Link will be relocating existing poles and pedestals at southwest and northwest corner of intersecti­on. Once relocation­s are completed, contractor will commence with new roadway improvemen­ts.

Road Closures: Road is open to vehicular traffic with two lanes of travel in each direction.

Motorists are encouraged to follow all traffic control signs.

Utility Work: 06/15/2020 thru 07/10/2020: Avenue C, between Highway 95 & Co. 16th St. USBR will be closing Avenue C in order to install new facilities. Detour will be thru Co. 15th St & Avenue B.

YUMA/MOHAWK VALLEY WORK SCHEDULED (06/08/2006/12/20)

GRAVEL ROAD MAINTENANC­E:

• Route 1: Co 11th St to Co 14th St between Ave H to Ave D½

• Co 17th St to Co 20th St between Ave J to Ave F and Cesar Chavez Ave

• Route 3: Ave 32E to Ave 35E between Co 7th St to Co 5th St

• Ave 35E to Ave 38E between Co 6th St to Wellton Kofa Rd

• Route 4: Ave 40E to Ave 45E between Hwy 80 to Co 5th St

• Ave 39E to Ave 47E between Co 5th St to Co 2nd St

WORK ZONE:

Guardrail Repair on Ave 5E & Co 13½ St

YUMA/MOHAWK VALLEY WORK SCHEDULED (06/15/2006/19/20)

GRAVEL ROAD MAINTENANC­E:

• Route 1: West Co 9th St to West Co 11th St between Ave G to Ave E

• West Co 11th St to West Co 14th St between Ave H to Ave E

• Route 3: South Ave 20E to

South Ave 22E between Co 8th St to Co 10th St

• South Ave 22E to South Ave 26E between Co 10th St and Co 11th St

WORK ZONE:

Overlay on Hwy 80 from Ave 45E to Ave 48E

SIGN MAINTENANC­E:

• Route 3: Co 3rd St to Hwy 80 from Hwy 95 to Ave 29E

• Co 6th St to Co 14th St from Ave 29E to Ave 36E

• Co 4th St to Hwy 80 from Ave 36E to Ave 45E

• Co 2nd St to Hwy 80 from Ave 45E to Ave 52E

• Dateland Ave

• Ave 64E

• Paloma Rd

• Hyder Rd

• Route 1: Hwy 95 to Ave B from Co 19th St to Co 15th St

• Co 15th St to Co 1St. St from Ave H to Ave B

• Ave B to Ave 5E from Co 21st St to Co 12th St

• Co 14th St from Pacific Ave to Araby Rd

PREVENTIVE MAINTENANC­E:

• Archibald & Urtuzuaste­gui

• Main & Uruzuasteg­ui

• Ave 4E & Co 4th

• Hwy 95 & Cocopah

WORK ZONE:

Guardrail repair – Ave 5E & Co 13½ St

Newspapers in English

Newspapers from United States