CITY ROAD REPORT
A weekly summary of City projects or encroachment permits issued by the City of Yuma affecting busy streets.
North End pavement replacement project
A contractor working for the
City will remove and replace street pavement, water lines, and Ada-standard sidewalk ramps on various streets in northern Yuma, roughly between Avenue A and 4th Avenue. Most of the major street reconstruction work is complete; however, work crews will continue to operate in isolated areas. Currently the contractor is raising utility accesses to grade level. The overall project is expected to conclude in summer 2024.
Avenue 5E, 37th Street to 40th Street
A contractor working for the City is installing water and sewer lines on Avenue 5E between 37th Street and 40th Street, plus new re hydrants and new service connections, followed by pavement replacement. Avenue 5E will be closed to through traf c between 32nd Street and 40th Street, and to all traf c between 37th Street and 40th Street. Detour using Avenue 4E or Avenue 6E. This project is expected to be complete by late April or early May.
45th Avenue, 24th Street to 28th Street
A contractor working for the City will construct a multi-use path along 45th Avenue between 24th Street and 28th Street. Most work will occur off the roadway; however, one phase of the project will prompt a closure of 45th Avenue between 24th Street and 26th Street. The project is expected to run through mid-april.
28th Drive, 31st Street to 29th Place
28th Drive traf c is restricted to northbound only between 31st Street and 29th Place for emergency storm drain repair.
Spring pavement preservation
Spring surface treatments are expected to run through the end of April. Impacted neighborhood property owners will receive a door hanger that indicates the area where the roadway maintenance is taking place as well as the dates and times. Find a complete list of roadways and subdivisions to be preserved on the Pavement Preservation page of the City’s website. This page provides an interactive map where residents can zoom in on highlighted streets and click for that street’s scheduled maintenance date.
Oil Seal April 22, Desert Sky 1 Subdivision
• 39th Place from Brianna Drive to 7341 39th Place • Brianna Drive from 39th Place to 39th Street • 39th Street from Brianna Drive to 7333 39th Street • 37th Place from Brianna Drive to 7333 37th Place • Brianna Drive from 37th Place to 3808 Brianna Drive • 38th Street from Brianna Drive to 7335 38th Street
April 23, Desert Sky 1 Subdivision
• Brianna Drive from 39th Street to 3808 Brianna Drive • 38th Lane from Brianna Drive to 7337 38th Lane
April 24, Desert Sky 1 Subdivision
• 37th Place from Desert Sky Drive to 7333 37th Place • 38th Street from Avenue 7 3/4E to 7335 38th Street • Desert Sky Drive from 37th Place to 3827 Desert Sky Drive
April 25, Desert Sky 1 Subdivision
• 39th Place from Desert Sky Drive to 7341 39th Place • 39th Street from Desert Sky Drive to 7333 39th Street • 38th Lane from Avenue 7 3/4E to 7337 38th Lane
CITY STREET MAINTENANCE
City Street Maintenance operations for March 25-31 will take place in the following areas:
Streets Concrete Sidewalk Repair
• Arthur Tongeland Subdivision
• Yuma Townsite
• Desert Ridge
Street Asphalt Patching
• County 17th Street from Avenue 1E to Avenue 4E
• Avenue 1E from County 16th to County 17th Street • La Mesa Linda
Streets Lane Striping
• Castle Dome Avenue from 12th Street to Yuma Palms Parkway • Pacific Avenue, 12th Street to 16th Street • 24th Street from 4th Avenue to Avenue A
OTHER UTILITY PROJECTS AND ENCROACHMENT PERMITS Avenue A, Parkview to 28th Street (Yuma County)
A contractor working for
Yuma County is working on the Smucker Park ood control basin, which will at times affect Avenue A between Parkview Loop and 28th Street. The sidewalk on the west side of Avenue A is closed. Motorists on Avenue A should be aware of trucks entering and exiting the roadway on the north side of the park. Later phases of work will include lane restrictions on Avenue A and a closure at Westridge, anticipated for early 2024. Message boards will be activated 72 hours prior to any such closure. Concrete pouring is expected at 28th Street and Avenue A on April 9. Fiber optic installations (Allo)
Communications line installations will take place in areas designated for utility easements within the City limits and surrounding vicinity in the following areas:
• Avenue B, 8th Street to 3rd Street
• Area between Avenue B and 15th Avenue, from West Main Canal to 8th Street
• Area between 1st Street and Giss Parkway, 4th Avenue to Gila Street
• Area between 12th Street to 14th Street, Pageant Avenue to 44th Avenue
• 24th Street and Kennedy Lane
• Las Casitas subdivision
• The Dunes subdivision
• Areas surrounding 8th Street to 47th Drive, including Donovan Estates
• 32nd Street between avenues 6E and 8E
• Avenue C and 16th Street
• Gila Ridge Road, east toward Avenue 6E
• Area between 2nd Street and 6th Street, Magnolia to 13th Avenue
• Area between 16th Street and 20th Street, from Avenue A to 5th Avenue
• 3rd Street west of 15th Avenue
• Hettema Street
• Arizona Avenue, 18th Street to 19th Street
Avenue 8-1/2E, 34th Street to 40th Street (Gila Electronics)
Installation of new ber optic cables will require a lane shift on southbound Avenue 8-1/2E between 34th Street and 40th Street through late April.
Maiden Lane, 1st Street to 2nd Street (Yuma County)
Installation of a construction crane will prompt the closure of Maiden Lane between 1st Street and 2nd Street.
Avenue B, 15th Street (Century Link)
Century Link has a 60-day project that will include a closure of the right southbound lane of Avenue B approaching 15th Street. Work is expected to conclude by mid-may.
24th Street, Paci c Avenue to Avenue 3E (SW Gas)
Gas line replacement work will include eastbound lane closures of 24th Street between Paci c Avenue and Avenue 3E. Work should complete in late April.
Riley Avenue B, 17th Street to 18th Street
Riley Avenue is currently closed between 17th Street and 18th Street for construction work.
40th Street/ County 12th Street, Avenue 5E (APS)
APS pole and line work will require lane closures at 40th Street/ County 12th Street at Avenue 5E the week of April 29 through May 3. Traf c will be regulated by ag persons.
Arizona Avenue, 25th Street (SW Gas)
Gas valve maintenance work will require a 15-day lane restriction on Arizona Avenue at 25th Street. Work should conclude by June 5.