Yuma Sun

COUNTRY ROAD REPORT

-

BY YUMA COUNTY Smucker Park Detention Basin

Smucker Park and adjacent property will undergo constructi­on for ood control measures. The park is located at 2913 S Avenue

A in Yuma, adjacent to S Avenue A between the Yuma Regional Medical Center and West 32nd Street. The project includes installati­on of new storm drainage and sanitary sewer systems, constructi­on of an embankment, street improvemen­ts, and ood mitigation measures such as installing a oodgate, oodwall, over ow spillway and pump station. Project work will occur Monday through Friday from 5 a.m. to 5 p.m. for approximat­ely one year.

Contractor poured concrete slab for culvert slab at 28th Street and will continue with preparatio­n to install walls and deck for box culvert. Also, continue installati­on of 4” irrigation line from Canal to

City facility. Contractor has also expected to continue dewatering for new 36” Sanitary sewer line and commence installati­on of new sewer line. Floodwall inspection­s completed as to allow contractor to commence placing forms for oodwall footing.

North Frontage Road from Avenue 10E to Fortuna Road Reconstruc­tion

Yuma County will reconstruc­t North Frontage Road to a 3-lane road with curb, sidewalk and bicycle lanes from Avenue 10E to Fortuna Road. In addition, a storm drain system will be installed to direct storm water runoff to two retention basins. Constructi­on began in July 2023. North Frontage Road is expected to remain open for most of the constructi­on, although road closures will be scheduled for certain portions of the work.

Vehicular traf c is now shifted to new pavement surface on North side of roadway. Contractor is placing the storm drain system from Cactus Propane to Caravan Oasis including the installati­on of several manholes and catch-basins. Contractor is also working on grading the East driveway and the parking area at the Day-breakers restaurant, they are scheduled to pave both areas by 05/03. After the parking area is paved, they will be placing concrete parking stops and will be striping the parking stalls.

LOS AMIGOS AND SOUTHERN SANDS DRAINAGE AND PAVEMENT IMPROVEMEN­TS

This project will include a new storm drain system along Avenida Compadres and valley gutters in Los Amigos. All roads in the Southern Sands & Los Amigos Subdivisio­ns will have the existing surfacing removed and new aggregate base course and new Asphaltic Concrete Pavement installed along with some miscellane­ous items.

Contractor to continue work in

Los Amigos, Southern Sands and Avenida Compadres. For the rst portion of the work contractor will be installing storm drain along Avenida Compadres, grading side streets at Los Amigos and completing concrete valley gutters along the side streets and concrete aprons at the Avenida Compadres intersecti­ons. They have been grading & placing aggregate base material in Los Amigos streets, they Paved 30th Place, 30th Lane and 31st Place last week. They are placing the concrete valley gutters & concrete aprons for 30TH Street, Compadre Lane, 29th Place and

29th Lane, they will be paving these four streets by 05/03. They are scheduled to apply base material for 31st Street, 29th Street, Compadre Place, 28th Lane & 28th Place, these streets will be paved in 2 weeks. Contractor started trenching along Avenida Compadres for the installati­on of the storm drain system. Contractor will start the removal of the asphaltic concrete pavement in the Southern Sands subdivisio­n late this week. They will be replacing the old aggregate base course with new aggregate base course and will be placing asphaltic concrete pavement in the next 2 weeks.

Road Closures:

Avenida Compadres is closed at the North Frontage Road intersecti­ons in order for the contractor to start the installati­on of the drain pipe system next week. Traf c is being detoured to County 10-1/2 Street and Avenue 10E.

RED CLOUD MINE ROAD

Roadway improvemen­ts begin at Martinez Lake Road and extend northeast 2.1 miles to Snipe Road. From Snipe Road a new alignment roadway was constructe­d for 1.1 miles to connect to Wildlife Way. The length of the project is 3.2 miles. Road improvemen­ts include grading, paving, drainage improvemen­ts (box culverts), and smoothing out the vertical alignment to improve safety and provide all weather access.

This project is complete except for one-half mile section, which was not constructe­d in accordance with the speci cations. The Federal Highway Administra­tion (FHWA) has engaged a contractor to make the required repairs to the pavement structure. The project will also include steel plates on the cattle guards to reduce vibrations and noise. It is anticipate­d the contractor will start work in April 2, 2024.

Red Cloud Mine Road has been reduced to a single lane using portable traf c signals. The contractor has completed installati­on of steel plates on the cattle guards to reduce vibrations and noise. Contractor has switched to using a pilot car during the placement of the gravel base material and applicatio­n of the prime coat. Milling of asphalt pavement is complete. Placement of gravel base is scheduled for this week and next week. Placement of asphalt pavement is scheduled to start on May 13, 2024 and it is scheduled to be complete by May 17, 2024. Constructi­on is planned to be complete by middle of June 2024.

YUMA/MOHAWK VALLEY WORK SCHEDULED (05/06/24 – 05/10/24)

YUMA EAST SECTION MAINTENANC­E:

Route 1: 19E to 21E from old Hwy 80 to Co 7th St

Route 2: 40E to 42E from Co 6th to Co 4th St

Route 3: 50E to 52E from Co 8th St to Co 4th St

Chip Seal:

Hwy 95 to 28E

Hwy 80 to Co 2nd St

YUMA WEST SECTION MAINTENANC­E: Route 1:

Co 16th St to Co 19th St between Ave J to Ave D

Route 2: Co 12th St to Co 8th St between Ave G to Ave B

Avenue D, from Levee road to Power Street

Co 11th St from Ave G to West Terminus

Co 12th St from Ave B to East Terminus

SHOP & SIGNAL MAINTENANC­E WORK SCHEDULED (05/06/24 – 05/10/24)

Route 1: Co 13th from Ave F to Ave H

Co 12th from Ave F to Ave H Co 12th from Ave F to Ave G

Ave F from Co 11th St to Co

13th St

Ave G from Co 11th St to Co

13th St

Ave H from Co 12th St to Co

13th St

Including all other road segments within these areas

Route 2:

24th St from Fortuna Rd to Camino del Sol

28th St from Fortuna Rd to Camino del Sol

S Frontage Rd from Fortuna Rd to 15E to Via Salida

Ave 111⁄2E from 24th St to 28th

St

Alameda Ave from 24th St to

28th St

Hensleys Blvd from S Frontage Rd to Via Canada

Via Salida from S Frontage Rd to Calle del Cid

Including all other road segments within these areas

Route 3:

Ave 39E from Co 6th St to Co 31⁄4 St

Ave 40E from Hwy 80 to Co

31⁄4 St

Co 6th St from Ave 38E to Ave 40E

Co 5th St from Ave 38E to Ave 40E

Co 4th St from Ave 38E to Ave 40E

Including all other road segments within these areas

PREVENTIVE MAINTENANC­E:

Foothills Blvd & 48th St

Foothills Blvd & 44th St

Foothills Blvd & 40th St

Foothills Blvd & 38th St

Fortuna Rd & 28th St

Fortuna Rd & 36th Pl

Fortuna Rd & 40th St

Fortuna Rd at Railroad Crossing S Frontage Rd & Payson Dr S Frontage Rd & Fry’s

Ave 12E & 40th St

Co 3rd St & Ave 16E

WORK ZONE:

Each section will respond.