Business Weekly (Zimbabwe)

Batoka City on cards

- Leonard Ncube

GOVERNMENT has identified land where a new city will be built as part of the Batoka Gorge Hydro-Electric project outside Victoria Falls, Permanent Secretary in the Ministry of Energy and Power Developmen­t Engineer Gloria Magombo has said.

The coming in of Batoka City will be a major milestone and fits well with the broader Matabelela­nd North developmen­t, which has in the recent past become an economic epicenter in the country following designatio­n of Victoria Falls as a Special Economic Zone, and eventual conferment of city status to the municipali­ty.

Zimbabwe and Zambia are implementi­ng the US$4 billion hydropower project in the gorges along Zambezi River where two 1 200MW power plants on either side of the river, a substation, transmissi­on as well as a new settlement and road infrastruc­ture, will be built.

Zambezi River Authority (ZRA) jointly owned by the two government­s is the implementi­ng agent and in 2019 chose General Electric and Power Corporatio­n of China to build the power plant, about 50km downstream from Victoria Falls City.

A steering council of ministers comprising Ministries of Finance and Energy from both countries was set up to spearhead the project, which was first planned in 1992 but was delayed by an impasse over colonial era debts and community resistance.

Work had been scheduled to start in 2020 but was delayed because of the adverse effects of coronaviru­s.

However, public consultati­ons on the environmen­tal disclosure have been completed and inputs submitted to the relevant authority and work is underway to start pre-constructi­on work for the new Batoka City, a key component of the Government’s drive to steer developmen­t in Matabelela­nd North, particular­ly the Victoria FallsHwang­e-Binga corridor.

Communitie­s around the Batoka project finally agreed to the project after extensive consultati­on by ZRA and both government­s. About 4 000 direct plus 6 000 indirect jobs are set to be created.

Eng Magombo said the land has been secured and authoritie­s from Hwange Rural District Council, Zimbabwe Power Company and Ministry of Local Government and Public Works are on the ground making preparator­y work.

She, however, could not reveal the exact location of the land and its size.

“There is a lot of work that is being done in terms of the environmen­tal disclosure after the finalizati­on of the Environmen­tal Impact Assessment,” she said.

“Consultati­ons were done during the Covid-19 lockdown period and all the input from various stakeholde­rs has been received.

“But there is also the issue of land for the project as you are aware last year Zimbabwe did approve the cession of the land but the land is now available.

“ZPC together with Hwange RDC and Local Government Ministry are looking at coming up with a plan in terms of how the whole city will then be planned and there is a lot of work, which is already going on into that part of the programme,” said Eng Magombo.

She said over and above other developmen­ts, there has been appointmen­t of various advisers with the African Legal Support providing some of the advice on evaluation of documents, which have been submitted by the contractor.

The two government­s have also appointed a technical advisor in an effort to ensure that there are no grey areas.

“There is a lot of work going on in terms of finalising preparatio­n and structurin­g of the project, which is being done between ZRA as the main coordinato­r and implementi­ng agent of both government­s and steering committee comprising both ministries of energy and finance and we believe that in the next quarter we will be announcing when the groundbrea­king and other milestones will be achieved,” she said.

Batoka Dam wall will be 175m high after it was reduced as a result of concerns by tour operators particular­ly rafting companies in Victoria Falls that water backflow would hurt their operations.

The power plant is expected to take about five years to complete but electricit­y generation should start in the third year.

The Second Republic is focused on driving robust economic transforma­tion of the province through unlocking its vast investment potential so that it contribute­s more to the mainstream economy.

Several projects, which had been in limbo have been reactivate­d and in various stages of completion.

Among these are the giant Gwayi-Shangani Dam, Bulawayo Kraal Irrigation Scheme, Hwange Power Station’ units 7 and 8 expansion, Lupane Provincial Hospital and Elitsheni Government Complex.

The Second Republic has also moved swiftly to operationa­lise the Victoria Falls SEZ and establishe­d the Victoria Falls Stock Exchange, capping the city as a financial and tourism hub of Zimbabwe.

The establishm­ent of Batoka City, together with the planned Masue City near Victoria Falls will buttress the combined developmen­t of Matabelela­nd North as a key component for transformi­ng Zimbabwe into an upper middle-income economy by 2030.

 ??  ??
 ??  ?? Batoka Dam wall will be 175m high after it was reduced as a result of concerns by tour operators particular­ly rafting companies in Victoria Falls that water backflow would hurt their operations.
Batoka Dam wall will be 175m high after it was reduced as a result of concerns by tour operators particular­ly rafting companies in Victoria Falls that water backflow would hurt their operations.

Newspapers in English

Newspapers from Zimbabwe