NewsDay (Zimbabwe)

Sinohydro restarts Hwange power plant facelift

- BY ANDREW KUNAMBURA/TINASHE KAIRIZA

ACHINESE firm undertakin­g the US$1,1 billion refurbishm­ent and expansion of Zimbabwe’s largest thermal power station says it has resumed operations on the project, seven months after constructi­on was halted by the COVID-19-induced lockdown.

Government­s worldwide have significan­tly eased lockdown regulation­s announced at the beginning of the year, allowing the shipment of critical equipment required to complete the project.

Sinohydro site manager Tang Zhaolai told NewsDay Business at the weekend that completion dates for the Hwange Thermal Power Plant would be moved forward by five months.

He said the project was 52% complete, against a target of 68%.

“Unit 7 was supposed to be commission­ed in October 2021, but will now be commission­ed in March 2022. Unit 8 will be commission­ed in June 2022 instead of the initial plan of January 2022,” Zhaolai told NewsDay Business.

“The good thing is that some of the equipment is shared and this means that once Unit 7 is completed, all efforts and resources will be directed to Unit 8. Everyone wants us to finish the project and deliver power. We cannot say we are satisfied, but we are doing our best to improve,” he said.

“The traffic has of late been smooth to allow smooth movement of equipment, mainly through South Africa. Every day we are getting truckloads of necessary equipment and this is encouragin­g,” Zhaolai said.

He said as part of its own coronaviru­s containmen­t measures, Sinohydro had offered accommodat­ion and food to its employees on site to restrict them from interactin­g with nearby communitie­s.

“We provide free accommodat­ion to all our employees on site, both the local ones and the Chinese. We also give them some allowances to help them sustain their families during this time,” he said.

“In a way we can say we imposed our own localised lockdown here and we even put up a perimeter fence to restrict movement and I think it has worked well because so far, we have not had any coronaviru­s case and work is going on smoothly. We invited the ministry of health to inspect our facilities and they made important recommenda­tions which we have fully implemente­d,” he said.

He added that the project was designed to preserve the environmen­t.

“For this project from design we were considerin­g the environmen­t. The filter installed will remove Sulphur dioxide which is emitted into the air by the old units,” he said.

The Hwange Thermal Power Plant is the largest project being undertaken by Zimbabwe under China’s Belt and Road Initiative through which Beijing seeks to fund bankable capital projects in developing countries, mainly in Africa.

On completion, it will add 600 megawatts (MW) into the national grid and significan­tly ease Zimbabwe’s power crisis.

Zimbabwe currently requires about 1 800MW during peak periods.

However, frequent breakdowns at existing power facilities have reduced production to less than 500MW.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Zimbabwe