NewsDay (Zimbabwe)

Mozambique kicks-off offshore gas project

-

AFLOATING plant for liquefying natural gas arrived in Mozambican waters on January 3 after a seven week maritime voyage from South Korea. Constructe­d by Samsung Heavy Industries (SHI), it is the first offshore project to come online in the nation’s embattled gas industry. It is also the first floating LNG facility to be deployed in the deep waters of the African continent, and the third in the world.

Lying above the 450 billion cubic meters (Bcm) of resources in the Coral field in Area 4 of the Rovuma Basin, the plant has the capacity to liquefy 3.4 million tons of natural gas per year from subsea gas producing wells per year.

Area 4 of the Rovuma Basin is operated by Italian oil and gas giant Eni, who signed a 20-year agreement to sell 100% of LNG production to British Petroleum (BP) in 2016.

The plant will extract gas from Area 4 of the Rovuma basin, located off the shore of the Cabo Delgado province of northern Mozambique, starting in the second half of the year.

Mozambique’s fledgling oil and gas industry has the potential to produce more than 30 million metric tonnes of LNG a year. But the country’s ambitions to join the ranks of the world’s largest LNG exporters have been thwarted by a growing Islamist insurgency in the gas-rich Cabo Delgado province that began in October 2017.

The project comes as Mozambique’s government assures oil majors that the security situation in the Cabo Delgado region is under control after four years of disruption and halted projects.

Most of the gas from the various projects is piped onshore for processing at the port of Afungi, which is vulnerable to attacks from terrorist group Ahlu Sunnah Wa-Jamamah (ASWJ).

The ASWJ, originatin­g in Cabo Delgado Province, launched violent attacks on villages before targeting the planned LNG scheme. More than 3 000 people have been killed and 820 000 have fled their homes.

In March, attacks close to gas sites prompted developer TotalEnerg­ies — the new name for French firm Total — to suspend work on the LNG plant by declaring force majeure, which will process gas for both of the main offshore gas consortia in the area. Billions of dollars of investment are at stake in a project that could transform Mozambique’s economic prospects.

The deployment in August 2021 of Rwandan military forces and the Sadc mission in Mozambique has allowed Mozambican security forces to make tactical successes.

In a State of the Nation address in December, President Filipe Nyusi assured investors that the government had made significan­t gains against the Islamic State affiliated Al-Sunna wa Jama’a (ASWJ) in the northern province of Cabo Delgado.

But an easing of security fears may be premature as ASWJ shifts its strategy and adopts more convention­al guerrilla tactics, expanding westward towards the neighbouri­ng province of Niassa, says Alexandre Raymakers, a senior Africa analyst at Verisk Maplecroft.

“President Nyusi’s optimistic analysis of the situation in Cabo Delgado is primarily driven by his desire to portray recent tactical successes as evidence that the tide has turned in Maputo’s favour and that the government can guarantee the security of LNG projects.

“Indeed, Maputo is hoping that high profile successes will entice LNG operators to resume their work, which have been suspended since March 2021.”

Remote and sparsely populated, Niassa is an ideal rear base for the insurgents to reorganise and develop a new supply line through Malawi and Southern Tanzania.

“The presence of a 2 000-strong Rwandan contingent will, however, reduce the frequency of attacks in the district of Palma, where TotalEnerg­ies’ Afungi LNG project is located. We expect Maputo to continue concentrat­ing its most capable military forces in the district in order to reassure TotalEnerg­ies that it can guarantee the security of its project,” Raymakers said.

TotalEnerg­ies will resume work in the next six months to assure shareholde­rs that the suspension was temporary, Raymakers said.

“However, the evolving threat posed by ASWJ means that the resumption of work at the project site remains outside the company’s control.”

The departure of regional forces would also likely lead to a rapid deteriorat­ion in the security situation, Raymakers adds.

“Although, SAMIM’s mandate is likely to be renewed this month, it is unlikely to last longer than 12 months due to the SADC’s limited ability to fund the mission.

“We, however, expect the Rwandan contingent to remain in place, protecting key LNG sites in Palma district, for the next 12 months at least.”