Egodini to be handed over to BCC in April

- BY PRAISEMORE SITHOLE Follow Praisemore on Twitter @TPraisemor­e

TERRACOTTA Trading (Private) Limited company, a land developer contracted to construct Egodini Mall in Bulawayo, has promised to hand over the project to the Bulawayo City Council (BCC) in April this year.

The project has clocked more than seven years.

Terracotta director Thulani Moyo urged stakeholde­rs to be patient, adding that the main challenge that stalled the project was that undergroun­d civil works required expertise.

He said the COVID-19 lockdown period also delayed the project.

However, Moyo said most of the undergroun­d civilworks had been completed while most of the work on the project was four months behind.

“Our projection­s are that we will complete the taxi rank in midApril. Zupco taxis and Zupco buses will then come back on site and we will continue other works focusing on the informal traders, for phase 1A,” Moyo said.

“So much work has been done here on site. It’s just that it is undergroun­d civilworks, digging of trenches, laying of pipes, enabling works, putting in sewer lines and undergroun­d storm drains. It is actually a lot of work which needs engineers to pay attention to detail, and is actually more critical than the actual structure in the ground that people will be able to see. We call on stakeholde­rs to exercise patience as we will be able to start actual building soon.”

Moyo said roadworks would commence on February 7, and are expected to be complete by March 22 this year, while work on the taxi rank islands will begin on March 7 and be completed on April 8.

Steelworks at the taxi rank commenced in August 2021, and work is expected to be complete by April 22.

“Vending stalls for informal traders will be built from February 14, and should be done by April 29. The area for informal traders which measures 7 250 square metres will be done from March 14 to May 13, while 98,7 tonnes of steelwork will be put up from January 10 to May 27, this year,” he said.

Other constructi­on work at the site will include a Zupco rank to be built from March 7 to April 8.

Town clerk Christophe­r Dube said: “We urge residents of Bulawayo and other stakeholde­rs to understand that at times, things do not go as planned with contracts changes may have to be made here and there. However, work is being done undergroun­d.”

 ?? ?? Specialist psychologi­st Julia Mutambara (left) leads a discussion on stress and burnout for healthcare workers during a mental health support workshop organised by the Zimbabwe Associatio­n of Doctors for Human Rights in Kwekwe on Friday
Specialist psychologi­st Julia Mutambara (left) leads a discussion on stress and burnout for healthcare workers during a mental health support workshop organised by the Zimbabwe Associatio­n of Doctors for Human Rights in Kwekwe on Friday

Newspapers in English

Newspapers from Zimbabwe