NewsDay (Zimbabwe)

Zimplats commences US$520m expansion

- BY MTHANDAZO NYONI

MINING giant Zimplats says its US$521 million smelter expansion and sulphur dioxide abatement projects have commenced and commitment­s for major contracts were made during the first quarter of this year.

The project includes constructi­on of a 38-megawatt (MW) furnace and an acid plant for the abatement of sulphur dioxide generated by smelter operations, Zimplats said in a quarterly report for the period ended March 31 2022.

It said implementa­tion of the 185MW solar project received board approval during the quarter.

“The 35MW Phase 1 plant at Selous Metallurgi­cal Complex is scheduled for completion in FY2024 (financial year). In total, the project has four implementa­tion phases with the final phase scheduled for completion in FY2027 at an estimated total project cost of US$201 million,” the report read in part.

It said the implementa­tion of the Mupani Mine developmen­t project, the upgrade of Bimha Mine and the constructi­on of the third concentrat­or plant progressed according to plan during the quarter, with a cumulative project expenditur­e of US$241 million incurred and commitment­s of US$130 million at period end, versus a combined budget of US$562 million.

Mupani and Bimha mines will replace Rukodzi, Ngwarati and Mupfuti shafts which will be depleted in 2022, 2025 and 2028, respective­ly.

Zimplats said the third concentrat­or would increase milling capacity by 0,9 million tonnes per year and is expected to be commission­ed in August next year.

In the period under review, a total of US$0,9 million was spent on exploratio­n projects, with a further US$1,8 million committed.

"Exploratio­n activities included mineral resource evaluation, comprising approximat­ely 5 740 metres of surface diamond drilling over existing projects on the two mining leases. Exploratio­n activities increased geological and geotechnic­al confidence in production schedules," the mining company said.

Total operating cash costs increased by 3% from the prior quarter, impacted by inflation on major production inputs. The report shows that a total of US$4,3 million was transferre­d from opening stocks to operating costs during the period as a result of the smelting of concentrat­es stockpiled during the routine furnace taphole inspection shutdown in the prior quarter.

This resulted in the cost of metal produced rising by 8% versus the prior quarter. Volume gains partly offset inflationa­ry pressures and resulted in 2% increase in unit cost from US$735 per ounce (oz) to US$752/ oz. Year-on-year unit cost increase of 6% reflected the mitigating benefit of higher production volumes on the 15% cost increase, the company said.

Mined volumes improved by 2% quarter-on-quarter and were 2% weaker year-on-year. The year-onyear decrease was mainly due to lower trackless mining equipment availabili­ty at Mupfuti Mine during the current quarter which has since been addressed. The new trackless equipment maintenanc­e service provider has now scaled up operations to optimum level, it said.

Milled tonnes decreased marginally to 1,71 million tonnes due to fewer operating days than in the prior quarter. Milled volumes were, however, stable year-on-year. 6E (platinum, palladium, rhodium, ruthenium, iridium and gold) metal in final product increased by 6% to 148 541 oz from the prior quarter and increased by 8% year-on-year.

Production benefited from a positive smelter inventory movement and the treatment of concentrat­es stockpiled during the furnace shutdown in the prior quarter.

Newspapers in English

Newspapers from Zimbabwe