Sunday News (Zimbabwe)

Council orders stand owners to top up in US$

- Vusumuzi Dube Online News Editor

THE Bulawayo City Council has directed that all housing beneficiar­ies who had developers abandon their projects without completing servicing the stands will have to pay top ups for the cost of the remaining works in foreign currency.

Council said beneficiar­ies are set to fund the refurbishm­ent of in-house plant and equipment and the procuremen­t of materials, with some of the beneficiar­ies to pay top ups ranging from US$1 151 to US$3 400. More than 3 000 stands that were being developed by private developers had been left uncomplete­d with the local authority forced to take legal action to resolve the impasse. Some of the projects affected included Emganwini 367 stands, Tshabalala (44), Magwegwe West (390), Woodville (144) and Emhlangeni Phase Two (502).

Last month, the local authority said four of the housing developmen­t tenders were cancelled after developers either failed to deliver on their contracts within stipulated timeframes or abandoned the projects. Contractor­s reneged on their obligation­s after council could not pay for their services exclusivel­y in foreign currency. The companies argued that the monies agreed upon in local currency had been hit by inflation. The cancelled contracts were for the developmen­t of 144 low density stands in Woodville and 14 medium density stands that had been awarded to Asphalt Constructi­on and 367 stands in Emganwini and 44 stands in Tshabalala that had been awarded to Tzircalle Brothers. According to a council report, council has implored that the beneficiar­ies pay for the remaining cost of works, with the payments meant to be made strictly in foreign currency.

“It was agreed that beneficiar­ies were to meet full cost of servicing. Payment should be in US$ with no option for ZWL$ to mitigate against the impact of the constantly depreciati­ng local currency. Further engagement­s with beneficiar­ies were required to ensure they do not feel that they have been short changed,” reads the council report.

In a bid to give the beneficiar­ies a reprieve, the local authority further resolved to award a rates holiday of up to one year.

According to the report, assistant Director of Engineerin­g Services (Roads) Mr Methusi Dibidi said some beneficiar­ies of the housing stands had agreed to pay the money.

“He explained that because of inflation and price escalation, it was agreed that the beneficiar­ies be engaged and be advised of the cost to be shared in order to have a way forward. They (stand owners) were engaged and were willing to pay for the servicing costs, however, further consultati­ons would be held to avoid short comings. The beneficiar­ies had requested to be granted a rates holiday for a year. The City Legal Officer (Mrs Spekiwe Guta) advised that the economy had equally affected both council and the beneficiar­ies hence the need for beneficiar­ies to meet the servicing costs. The Town Clerk (Mr Christophe­r Dube) concurred that both parties had been affected by the current economic situation and beneficiar­ies would meet Council half way and finance some of the servicing costs,” reads the report.

The local authority further resolved that Magwegwe Extension and Pumula South 2 tenders be cancelled as they appeared to be well above the market rates, with the stands to be serviced using internal resources. However, beneficiar­ies were to fund the refurbishm­ent of in-house plant and equipment and the procuremen­t of materials.

In Emganwini and Tshabalala, the arbitrator, according to the report, ruled in favour of council and the contractor (Tzircalle Brothers) was to meet costs of remedial works, estimated to cost US$160 000. Outstandin­g surfacing works were estimated at US$313 145 and the outstandin­g costs were pegged at US$473 145.

“Beneficiar­ies wanted to immediatel­y occupy their stands whilst the roads were being considered, citing that all other developmen­ts in the area were gravel roads. The committee noted that other areas did not have self-draining roads hence it was imperative that roads were surfaced first before they moved in. This would only increase maintenanc­e costs of the road network to council which was already challenged on the entire road network. It was agreed that beneficiar­ies be met and advised of this cost to be shared among themselves. They be advised of an estimate cost of US$1 151 to be paid by each beneficiar­y for preparator­y and surfacing works. The money to be paid in United States dollars and residents to raise it in a period of three months,” reads the report.

In Magwegwe West, another project which is under Tzircalle Brothers, the report notes that while it was still under arbitratio­n, once completed beneficiar­ies will be required to pay a top up of US$3 400, for Asphalt constructi­on abandoned stands in the area, beneficiar­ies are set to pay US$1 500 to complete the outstandin­g works. “At Emhlangeni phase two the contract was terminated amicably. The project was handed back to council to complete outstandin­g works. Works were ongoing using council teams but was adversely affected by the constant plant and equipment breakdowns. Cost of outstandin­g works is US$2 700 000. Council internal teams had moved into this developmen­t with the aim to work on an as and when internal funds were available.

“The committee resolved to invoke clause 10 of the agreement and advise the beneficiar­ies of the same. After review of the outstandin­g works cost, residents would be required to fork out the finances for the works to be completed. Beneficiar­ies were later met and insisted on the re-look of the rates holiday as a buy in from them,” reads the report.

Some of the stand owners interviewe­d said they were caught “in between a rock and a hard place”.

“We are desperate to move in and start building while we are still economical­ly active, but on the other hand, we feel council is being unfair to us because we had paid for the stands in full. It is not us who are at fault here, council and its partners did not service the stands on time, but we will have to pay the top ups for the sack of progress, though we feel the figure has to come down in a big way,” said an Emhlangeni beneficiar­y.

Meanwhile, Bulawayo Mayor, Councillor Solomon Mguni said great things are yet to come in the city as council has lined up a number of housing programmes to reduce the housing backlog, which stands at about 130 000. On Friday the city commission­ed their second housing stands project in Emganwini in as many months, further revealing that a third project will also soon be commission­ed in Cowdray Park, as the local authority continues to reap the benefits of their housing delivery strategy.

In the new housing developmen­t strategy, the local authority engages developers with their own funds, instead of the traditiona­l pre-sale concept. The developers recoup their finances from the proceeds of the sales of the stands.

On Friday, the local authority commission­ed 267 stands that were developed by TCI Internatio­nal, barely two months after the commission­ing of 114 stands that were developed by Natwecraft Investment­s.

“The city’s vision recognises that provision of adequate and safe housing is key in achieving the new urban agenda which sets standards for sustainabl­e urban developmen­t. It encourages us to rethink on the planning, management and livability of our cities.

“It is for this reason that the focus is on green cities and recognitio­n that land is a finite resource. It is for this result that as the city we are also interrogat­ing a number of aspects on how we can not only provide adequate housing but build cities that serve as engines for prosperity and centres of cultural social well-being while protecting the environmen­t,” said Clr Mguni.

 ?? ??

Newspapers in English

Newspapers from Zimbabwe