The Herald (Zimbabwe)

Council sets up probe team

- Freeman Razemba Senior Reporter

HARARE City Council has set up a seven-member team to probe rehabilita­tion costs of more than $13,8 million for digesters at its biggest sewer treatment plant, Firle Sewage Works, by a local contractor, ERAC. This comes after councillor­s noted the project had taken too long to complete. The council’s Environmen­tal Management Committee minutes indicate the investigat­ive team comprises four councillor­s and three external experts.

HARARE City Council has set up a seven-member team to probe rehabilita­tion costs of more than $13,8 million for digesters at its biggest sewer treatment plant, Firle Sewage Works, by a local contractor, ERAC.

This comes after councillor­s noted the project had taken too long to complete. It was initially set to start in April 2011 and end in October last year.

The council’s Environmen­tal Man- agement Committee minutes indicate the investigat­ive team comprises four councillor­s and three external experts — an engineer, a lawyer and an accountant.

Harare Water Department director Engineer Christophe­r Zvobgo told the committee that on March 22, 2011, the Procuremen­t Board awarded a contract to ERAC for the rehabilita­tion of sewage works at a cost of $13 816 117,10 paid in monthly instalment­s of $300 000.

“The project was supposed to be started in April 2011 and completed in October 2015. However, this could not be achieved due to financial constraint­s and as at 10th December 2015 about 40 percent of the project had been covered and a total of $5 500 157,19 had been paid as detailed in the report,” read part of the minutes.

Eng Zvobgo reported that the payments were being effected as and when funds became available.

“The equipment which was rehabilita­ted had been operating since 2011 and had gone beyond defects liability period, the breakdowns now required additional funding for the plant to continue operating. Project administra­tion under such a payment scheme was extremely difficult as planning could not be done,” according to the minutes.

“The main treatment plant units (BNR Units and Biological Filters) were now more than 90 percent operationa­l but not even a single digester was 100 percent complete to be able to stabilise sludge to required standards. The three digesters currently being used were functionin­g as storage tanks. Sludge from Firle Sewage Works was now the major health risk to the environmen­t and handling of sludge at the plant had to be addressed urgently.”

The Environmen­tal Management Committee noted that the City of Harare had already sent instructio­ns to the contractor to carry out critical works, which were done.

It was noted that a claim for payment for the work was submitted and the Harare Water Department had not yet evaluated it since it had only one signature.

“The Director of Works was recommendi­ng serving a notice of terminatio­n of the engagement as the parties were now working independen­tly and work progress had been affected seriously and the company was now dysfunctio­nal,” according to the minutes.

This led to the council setting up the seven-member committee to investigat­e the matter.

Newspapers in English

Newspapers from Zimbabwe