The Herald (Zimbabwe)

ZPC, INTRATREK DISPUTE RAGES ON:

- Business Reporter

INTRATREK Zimbabwe, which is entangled in contractua­l dispute with Zimbabwe Power Company (ZPC) over the Gwanda solar plant, has filed submission­s to the High Court seeking an order compelling ZPC to allow it to fulfil terms of the project agreement or be paid $25 million damages for breach of contract.

This comes after a dispute arose regarding fulfilment of terms of the contract, including stage-based payments due for part of work it has done, with the State power utility, however, claiming Intratrek failed to implement the 100 megawatt Gwanda solar project within agreed timeframes. Intratrek disputes this. The firm claims it had fictionall­y fulfilled terms of the contract and that challenges that delayed project implementa­tion as originally envisaged, were caused by ZPC, which also allegedly frustrated alternativ­e efforts to expedite the power project.

The company, which partnered multi-billion dollar asset firm and Shanghai Stock Exchange listed CHiNT Electric for the Gwanda project, submitted that it was clear from the outset ZPC had no intention to implement the contract in good faith, as demonstrat­ed by its failure to prove what it had done to facilitate project implementa­tion.

Apart from refusing to make further payments for the works Intratrek has done on the Gwanda solar project site, other than advance payments it made earlier, ZPC has allegedly threatened to cancel the contract citing delayed implementa­tion.

In its heads of arguments filed before the High Court last month under case 8159 /2018, Intratrek said ZPC was now seeking to set up a breach of contract scenario between the parties to avoid making payments, which it said were now due to it.

Intratrek wants ZPC held to its bargain and perform its part or alternativ­ely pay damages ($25m). The matter is likely to be set for hearing on November 16, 2018.

Before the dispute, the parties signed an addendum to the main contract in September 2017 for ZPC to pay sub-contractor­s of Intratrek directly in an effort to pace up the project, a subpact the former allegedly violated and further threatened to cancel the whole contract alleging contract violation through project delays.

In the heads of argument submitted to the High Court, top Harare lawyer Advocate Lewis Uriri said in the Government procuremen­t context, the remedy of specific performanc­e was available against both the organ of State and the contractor.

He said that a court of law could order the organ of State to pay the contractor, not interfere with the work of the contractor or delay the contractor in the performanc­e of its work.

“This accordingl­y is a motion for specific performanc­e of the agreement between the parties. In the alternativ­e, the applicant seeks damages that were within reasonable contemplat­ion of the parties at the time of contractin­g and the quantum of which is common cause or has not

been seriously disputed. The amounts to be paid in either case are largely contractua­l sums that are easily establishe­d on papers,” Intratrek said.

“The breach is self-evident on the papers. The applicant is entitled to hold the respondent to contract, alternativ­ely to seek damages. This is settled and trite position of the law.”

However, apart from claims of alleged breach of contract by either part, ZPC has also challenged the lawsuit by Intratrek at the High Court saying the case brought against it should have been brought to court by way of action instead of notice of motion.

But Intratrek shot down the claims as baseless and designed to delay resolution of the case.

“The objection is without merit. It is cosmetic. It is predicated on a lack of appreciati­on of the fact that on the papers the facta probanda is either common cause or cannot be seriously disputed.”

Intratrek argued that there were no material disputes of fact incapable of resolution on the papers by the court, adding the matter advanced and pleaded by it was clear.

“In view of the foregoing, it is submitted that there is nothing that stops this court from deciding the present matter on papers. The respondent (ZPC) has not proved and cannot prove that there is material dispute of fact incapable of resolution on papers.

“Even if it were to be assumed that there are material disputes of fact, there is nothing that precludes this court from employing the robust approach in resolving the matter.”

Intratrek submitted that it had performed part of the pre-commenceme­nt works that entitled the company to payment, which payment was stage-based in terms of the contract.

“The parties are agreed as to the extent of performanc­e reached by the applicant. More particular­ly the respondent never denies that the applicant submitted a report showing that it had performed 82 percent of the geotechnic­al survey.

ZPC does also not deny the fact that Intratrek had completed 33 percent of site fencing and that the contractor was due to be paid an amount of $120 333,34, although the whole job was valued at $181 277,58.

The contractor had also done part of ground clearance, which ought to be paid.

Intratrek also dismissed claims by ZPC that there were two contracts governing the agreement between the parties, arguing attempts to rely on provisions of the addendum of September 21, 2017 to vary terms of the original agreement was a misinterpr­etation of the contract, as the addendum only supplement­ed the original contract.

The company said reasons cited by ZPC for refusing to pay for works done at specific stages consisted of implausibl­e facts, bald and uncreditwo­rthy denials and untenable disputes of fact.

“It is not in dispute that the applicant’s (Intratrek) sub-contractor­s performed their obligation­s in terms of addendum number one. In particular, geo-technical survey and a final report were submitted to (ZPC) in or around July 2018.

“The respondent accepted the report and acknowledg­ed its findings. In respect of ground clearance, at least 85 hectares of land was cleared and de-stubbed. The first phase of fencing was completed in terms of provisions of the amended schedule 11 to the EPC contract.

“It is not contested that upon presentati­on of the invoices by (Intratrek) for payment by respondent (ZPC), the respondent flatly refused to pay the same citing reasons not founded in the contract,” Intratrek said.

The firm said the foregoing showed that a case for specific performanc­e was clearly made out, as ZPC could not prove material dispute of facts to deny the court from resolving the dispute between the parties.

 ??  ?? A solar farm. ZPC has allegedly threatened to cancel its contract with Itratrek citing delayed implementa­tion of the Gwanda solar project
A solar farm. ZPC has allegedly threatened to cancel its contract with Itratrek citing delayed implementa­tion of the Gwanda solar project

Newspapers in English

Newspapers from Zimbabwe