The Herald (Zimbabwe)

Works begin on Hwange units 7, 8

- Michael Tome Business Reporter

HWANGE Power Station units 7 and 8 expansion project, launched by President Mnangagwa at the beginning of August this year, has commenced with a number of civil works now underway.

The project will cost $1,48 billion and is expected to deliver an additional 600 megawatts; 300W from each unit, on top of the average of 450MW the old power station is currently able to generate.

Hwange power station has installed power generation capacity of 920MW, but is only able to churn out 450-500MW due to the advanced age status of the power plant, which was built in the early 80s.

The new project encompasse­s constructi­on of a 600MW base-load power plant and high voltage transmissi­on lines spanning over 350 kilometres from Hwange to Insukamini and Marvel sub-stations in Bulawayo.

The scheme is one Zimbabwe’s power projects financed under a loan facility from China Export Import Bank. State power utility Zesa Holdings, through its generation arm, is implementi­ng the project.

ZESA spokespers­on Fullard Gwasira told The Herald Business that initial constructi­on works were already taking shape particular­ly geo-technical surveys and excavation­s for the main power island buildings.

“Works in progress include the constructi­on of campsites, project offices, detailed geo-technical investigat­ions, excavation­s for boiler and turbine house, setting out of the transmissi­on lines, excavation­s for the sub stations and finalisati­on of detailed,” said Mr Gwasira.

As a result of the developmen­ts evacuation of families whose places of residence fall under constructi­on sites has already started. Consequent­ly, ZESA’s power generation unit, the Zimbabwe Power Company (ZPC) will resettle the affected households especially those situated along transmissi­on lines.

“ZPC is also implementi­ng the Resettleme­nt Action Plan for all people affected by the new transmissi­on lines and we recently completed extensive consultati­ons with key stakeholde­rs and affected parties,” he said.

With a projected duration of 42 months from 1 August this year, the Hwange expansion project demonstrat­es government’s drive to spur economic growth through implementa­tion of infrastruc­ture projects.

The project will result in massive socio-economic transforma­tion through increased power supply to the mining, agricultur­al and manufactur­ing sectors and has to date created about 260 jobs at the Hwange site while a further 4 000 people from surroundin­g communitie­s will get jobs.

Zimbabwe is draining limited foreign currency reserves through electricit­y imports, hence the need to prop up local power generation.

Newspapers in English

Newspapers from Zimbabwe