The Manica Post

. . . US$28m to polish up resettleme­nt site

- Ray Bande Senior Reporter

THE cost of finishing the constructi­on of houses for Cyclone Idai victims at Runyararo Relocation Site will gobble a further US$28 million.

Upon the completion of the first phase, a total of 224 households will have modern four-roomed houses sitting on half a hectare stand and another two and half hectares for farming.

While 173 units had been completed as of Wednesday last week, provision of water, sanitation facilities, irrigation developmen­t, livelihood­s projects, housing and roads are still work in progress.

According to a consolidat­ed budget for developmen­t of Runyararo Relocation Site, sanitation facilities need

US$225 032, while irrigation developmen­t will chew up US$65 500. Livelihood­s projects will cost US$11 812. Water supply and housing will cost US$24 million and US$3 691 097, respective­ly.

Roads are expected to cost US$263 115. In an interview on the sidelines of a tour of recovery projects in Chimaniman­i and Chipinge districts which was organised by the Manicaland Civil Protection Unit (CPU) on Wednesday, Deputy Director (Coordinati­on) in Minister of State for Manicaland Provincial Affairs and Devolution’s office, Mr John Misi said Government is happy with the progress made so far in the Cyclone Idai recovery process, even though much more work still needs to be done. Mr Misi said the main purpose of the tour was to appraise developmen­t partners of the existing gaps in the recovery process to avoid uncoordina­ted approach in interventi­ons. “The major purpose of the tour was to provide a clear understand­ing of progress and the interventi­on gaps that exist in the Cyclone Idai recovery process. Our partners have had an appreciati­on of the interventi­on gaps that exist in the recovery process and that is key in deciding how they can come in to compliment Government efforts,” said Mr Misi.

He added: “We also noted the challenges at Runyararo. Progress has been tremendous, but water provision remains a challenge. Our partners also noted this and some are eager to chip in. The long term solution to the water challenges at Runyararo will be the constructi­on of a dam along Umvumvumvu River.

“However, we are happy with the progress made in this recovery process and hopefully the remaining gaps will now be addressed from an informed point of view,” said Mr Misi.

On Wednesday, developmen­t partners and officials from several Government department­s toured Runyararo Relocation Site, roads and bridges repaired under the Cyclone Idai Recovery Plan, Mhakwe River Weir and schools that were affected by the cyclone.

The officials also toured Nyabamba and Kondo evacuation centres, as well as other places that were badly affected by the March 2019 cyclone in Chimaniman­i and Chipinge.

 ?? — Pictures: Tinai Nyadzayo ?? Runyararo Primary School is under constructi­on and three blocks have already been completed. Officials are optimistic that the institutio­n will open its doors to learners next year.
— Pictures: Tinai Nyadzayo Runyararo Primary School is under constructi­on and three blocks have already been completed. Officials are optimistic that the institutio­n will open its doors to learners next year.

Newspapers in English

Newspapers from Zimbabwe