The Sunday Mail (Zimbabwe)

Hwange 7 and 8 on course

- Kuda Bwititi Chief Reporter

THE US$1,2 billion expansion of Hwange Thermal Power Station’s units 7 and 8 is making steady progress, with hundreds of mainstream jobs created so far while close to $150 million has been invested in the first phase of implementa­tion.

At least 3 000 jobs are expected to be created under the project, which has been identified as one of the key economic enablers as President Emmerson Mnangagwa’s administra­tion advances its vision of turning Zimbabwe into an upper middle-income economy by 2030.

The project, which will add 600MW to the national grid, will take Zimbabwe closer to its plans of exporting electricit­y within three years.

Giving an update on the project’s progress to The Sunday Mail, Energy and Power Developmen­t Minister Dr Jorum Gumbo said the US$144 million recently availed for the project had given oomph to the expansion plans.

“It is one of the projects that we have placed under the Rapid Results Initiative. The project has received a facility of $144 million from China Eximbank. The status is that the work towards draw-down modalities and clearance of the conditions precedent is in progress.

“On its own Hwange was allocated an initial $78 million which will accumulate to $144 million over three years; the main conditions precedent being the signing of the agreements by the ring-fenced customers who form part of the securitisa­tion of the loan.”

Dr Gumbo said China’s government was fully behind the project, with Sinohydro the main contractor and China Eximbank providing the bulk of funding.

The minister added, “Commenceme­nt on the project started on August 1 and the RRI work plan is already done.

“Sinohydro has commenced on detailed designs and reviews of designs. There is also the issue of transmissi­on and distributi­on works. Contractor has submitted conceptual designs, revised documents for substation­s and power line documents.

“Regarding the work site, temporary works for warehouse foundation for Sinohydro staff dormitorie­s and canteen constructi­on, all these works are estimated to be at about 60 percent complete.

“For the actual power plant, excavation­s for coal-handling site, boiler house and machinery area, pulling tower and workshop area, ash layering and pipe rerouting are all in progress at about 78 percent.

“A detailed geo-technical investigat­ions report in preparatio­n for detailed designs has been generated and circulated.

‘‘The final report is to be submitted by Sinohydro this month.”

Dr Gumbo said Zimbabwe Power Company officials would soon be in China for due diligence assessment of subcontrac­tors.

He said Hwange 7 and 8 expansion had been accorded National Project Status in line with its significan­ce to the economy.

Sinohydro Zimbabwe MD Mr Wu Yifeng said they were satisfied with progress.

“The project is making progress on the schedule. China Eximbank has made the first disburseme­nt with the amount of about $150 million,” he said

“The contractor, Sinohydro, is busy on the procuremen­t of main manufactur­ing equipment in China. On the site, Sinohydro and ZPC engineers are working hard to close the designs and technical specificat­ions.

“At the same time, a temporary camp has been constructe­d and earth levelling works is ongoing in preparing for excavation of plant foundation.”

Sinohydro was behind the Kariba South Expansion that took just 14 months to complete, adding 300MW to the national grid.

The Hwange project was one of several developmen­ts prioritise­d for implementa­tion when President Mnangagwa met China’s President Xi Jinping in Beijing this year.

 ??  ?? Hwange Thermal Power Station conceptual design
Hwange Thermal Power Station conceptual design

Newspapers in English

Newspapers from Zimbabwe