Demand for details with bridge plans

- DAVID BENIUK

A FINAL business case for the new $576 million Bridgewate­r crossing will be submitted in coming weeks, as Infrastruc­ture Australia warns too many projects are being funded without one.

The Turnbull and Hodgman government­s committed to the long-awaited bridge this year, with a time frame to have it completed by 2024.

Estimates committees heard a final business case for the crossing remained outstandin­g after a draft was submitted to Infrastruc­ture Australia last year.

The State Government is adamant it will be lodged soon and that a planning team is being assembled.

“The verified business case will be lodged with Infrastruc­ture Australia in coming weeks,” a government spokeswoma­n told the Mercury.

“Work is also under way to establish a dedicated team to conduct the complex design, planning and approvals phase of the new bridge project.”

The Federal Government pledged $461 million — 80 per cent of the project’s funds — in its May budget, with State Treasurer Peter Gutwein adding $115 million in his budget in June.

The State Budget included $6 million of joint funding in 2018-19 to get a project team started on the design.

Constructi­on is scheduled to begin in 2021-22 and be completed in 2024.

Federal Labor leader Bill Shorten pledged $100 million to get the project started before the Liberal government­s stumped up the full amount.

The final business case will arrive as Infrastruc­ture Australia warns about government­s jumping the gun with funds for major projects.

Infrastruc­ture Australia Chief executive Philip Davies recently suggested that the body’s list of goals was being politicise­d.

“Too often we are still see- ing instances of projects being committed to before a business case has been prepared, a full set of options has been considered, and rigorous analysis of a potential project’s benefits and costs has been undertaken,” Mr Davies said.

Opposition infrastruc­ture spokesman David O’Byrne said the State Government should have completed the full business case.

“The State Government clearly hadn’t done the work so the Federal Government made the announceme­nt to get this State Government out of jail on inaction around the bridge,” Mr O’Byrne said.

“Now they’re scrambling to get together the work that should have been done years ago.”

Mr O’Byrne said the project risked running over time and blowing out in cost.

The Hodgman Government has released a 10-year, $13.9 billion infrastruc­ture plan, and promised a 30-year infrastruc­ture strategy.