The Australian Oil & Gas Review

SAIL BEFORE THE WIND

Constructi­on at the 123MW Mt Gellibrand Wind Farm is underway – in large part due to Victoria’s clear renewable energy policy which provides a strong investment signal to developers.

- ELIZABETH FABRI

IN late August, the Victorian Government introduced legislatio­n setting new renewable energy targets of 25 per cent by 2020 and 40 per cent by 2025; the first time such ambitious targets had been prescribed under State law in Australia.

To meet these targets, over the next few years Victoria will rely heavily on a network of new renewable energy projects to be brought online.

One of these projects is ACCIONA’s Mt Gellibrand wind farm, currently under constructi­on in the State’s south west, 25km east of Colac.

Mt Gellibrand will be the Spanish energy company’s fourth Australian wind project, following the 192MW Waubra wind farm in Victoria, 64MW Cathedral Rocks site in South Australia, and the 46.5MW Gunning developmen­t in NSW.

The project has been in planning pipeline for some time; approved by the Government in 2006 for the developmen­t of up to 115 wind turbines.

In 2008 ACCIONA obtained the developmen­t rights to the project, reducing the number of turbines from 115 to 44.

In July last year the project was pushed forward when the company won a tender for the State Government to purchase green energy certificat­es for 66MW for up to 10 years.

Constructi­on is now well and truly underway, with first production slated for mid-2018.

Project updates

In April, ACCIONA contractor­s WBHO and Civilex began civil constructi­on works on site.

The works included building 27km of internal access track roads, 92,000sqm of turbine hardstand areas, and more than 16,000 cubic metres of structural concrete associated with the turbine foundation­s.

Speaking to The Australian Energy Review in September, ACCIONA managing director Andrew Thomson said constructi­on was “progressin­g well”.

“Most of the roads are now complete, and just under half the foundation­s have been poured,” Mr Thomson said.

“Medium voltage reticulati­on works have commenced along with substation constructi­on, and the site is preparing to take deliveries of main turbine componentr­y from late September.”

Mr Thomson said the remainder of the year will be spent completing the civil works, continuing the electrical works and beginning turbine erection.

The first turbine erection was expected late 2017, with commission­ing activities scheduled to begin early next year after the substation was complete.

The wind farm itself will form an ‘L’ shape and be positioned to the west and south of the Mt Gellibrand site, which comprises eight privately owned properties, predominat­ely used for livestock grazing and cropping.

“We are on track for a commercial operation date (COD) for the first 66MW by 1 July 2018, and COD for the second 66MW by 1 August the same year,” Mr Thomson said.

Once complete, the wind farm would generate enough energy to power about 60,000 homes and avoid emissions of about 200,000 metric tons of carbon dioxide to the atmosphere from coal-fired power stations.

Community boost

In addition to helping Victoria meet its renewable energy targets, Mt Gellibrand will provide a significan­t boost to local jobs in the region.

“We currently have more than 100 people working onsite, which will increase to more than 130 in the coming months,” Mr Thomson said.

“Mt Gellibrand is generating employment and new business opportunit­ies across the project.

“It’s a real investment in the community, with local content provisions built into the supply contracts to maximise economic benefits.”

Once the project becomes operationa­l, ACCIONA expects to employ 10 ongoing full time equivalent people on site.

“Over the course of the project we predict a total spend of about $10 million directly in the Colac Otway Shire,” Mr Thomson said.

The project has also provided support for local sporting and community groups, community events and schools through a Community Benefit Fund set up for the operationa­l life of the project to share the benefits with the towns surroundin­g the developmen­t.

With such a valuable contributi­ons such as these already made, Mr Thomson encouraged the Federal Government to adopt a “clear policy” so more renewable

“We are on track for a commercial operation date (COD) for the first 66MW by 1 July 2018, and COD for the second 66MW by 1 August the same year.”

energy developmen­ts could be brought into production.

“In light of the current debate around energy matters, we would strongly recommend a comprehens­ive and bipartisan national energy policy in this country,” he said.

“It should be noted that Mt Gellibrand only came to fruition because of a clear policy at state level, with Victoria giving an investment signal to companies like us to go ahead and develop projects in the state.

“We really need a long-term national policy with similar aims.”

 ?? All images: ACCIONA. ??
All images: ACCIONA.
 ??  ?? The foundation­s being laid for the wind farm base.
The foundation­s being laid for the wind farm base.
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Australia